Do not use a wire rope cable that is kinked, frayed or has worn spots. Wear gloves when handling the wire rope cable. |
Show/hide table
NOTICE |
---|
Use 6 x 25 filler wire, right regular lay, independent wire rope core, pre-formed, improved plow steel-type cables. The wire cables should have a minimal breaking strength of 26672 kg (58800 lb) |
Show/hide table
SPECIFICATIONS     | ||
---|---|---|
Boom Length     | Diameter Of The Cable     | Length Of The Cable     |
6.1 m ( 20 ft)     |
19.05 mm (.75 inch)     |
40.2 m (132 ft)     |
7.3 m ( 24 ft)     |
19.05 mm (.75 inch)     |
45.1 m (148 ft)     |
Weld the cable ends in order to prevent fraying.
- Lower the boom to the ground and support the boom.
- Disconnect the cable from the drum for the boom. Remove the old cable.
- Unroll the new cable from the spool.
- Install the cable to the drum for the boom. Insert the end of the cable downward through the slot in the drum. Form a loop and insert the cable end upward through the slot. Insert the wedge into the loop in the cable. Pull the cable in order to seat the wedge and the cable in the pocket.
Show/hide table
NOTICE |
---|
Unroll all of the cable from the spool. Lay the wire rope on a flat surface. Never lift the wire rope off the spool in coils. |
Show/hide table
Illustration 1 | g00429470 |
- Wind one half of the cable on the drum. Wind the cable evenly across the drum.
- Install the cable from the winch to sheave (1) in the upper sheave block. Install the cable over sheave (1) from the front of the machine toward the rear of the machine.
Show/hide table
Illustration 2 | g00608160 |
(A) Cable from the winch (B) The arrow points toward the front of the machine. |
- Install the cable under sheave (2) in the lower sheave block.
- Install the cable over sheave (3) in the upper sheave block.
- Insert the cable into the pocket and around wedge (4) . Use a mallet to tap the wedge and the cable into the pocket.
Show/hide table
Illustration 3 | g00608221 |
- Insert the cable end through clamp (5) . Tighten the nuts on the clamp.
Caterpillar Information System:
DASA 280 Measuring and Control System Setting Module
3003, 3013, 3014 and 3024 Engines for Caterpillar Built Machines Fuel Injection Nozzles
3176C and 3196 Engines for Caterpillar Built Machines Rear Power Take-Off (RPTO)
572R Pipelayer Hook Load Line - Install
DASA 280 Measuring and Control System Programming Variables
793C Off-Highway Truck Machine Systems Double Check Valve (Rear Air over Hydraulic Cylinder) - Remove and Install
793C Off-Highway Truck Machine Systems Double Check Valve (Front Air over Hydraulic Cylinder) - Remove and Install
793C Off-Highway Truck Machine Systems Double Check Valve - Assemble
793C Off-Highway Truck Machine Systems Double Check Valve - Disassemble
793B Off-Highway Truck Steering System Solenoid Valve (Steering)
793C Off-Highway Truck Machine Systems Double Check Valve (Service and Secondary Brake) - Remove and Install
3126E and 3126B Commercial and Truck Engines Belt Tensioner - Inspect - If Equipped
IT14G Integrated Toolcarrier and 914G Wheel Loader Machine Systems Coupler Cylinder - Remove
793C Off-Highway Truck Machine Systems Hoist and Brake Hydraulic Breather - Remove and Install
784C and 785C Off-Highway Truck/Tractors Steering System Oil Filter - Replace
3003, 3013, 3014 and 3024 Engines for Caterpillar Built Machines Fuel Injection Pump
793C Off-Highway Truck Machine Systems Brake Light Pressure Switch - Remove and Install
DASA 280 Measuring and Control System Programming Times
784C and 785C Off-Highway Truck/Tractors Ether Starting Aid Cylinder - Replace
3126E and 3126B Commercial and Truck Engines Fuel System - Prime
793C Off-Highway Truck Machine Systems Relay Valve (Brake) - Assemble
631E Series II Wheel Tractor-Scrapers Radiator Core - Clean
CP-563D, CS-563D and CS-583D Vibratory Compactors Leveling Blade General Information
IT14G Integrated Toolcarrier and 914G Wheel Loader Machine Systems Coupler Cylinder - Install