Usage:

HH45 2JZ
The "Production" sub-menu can be used to perform the following functions:

  • Print production reports.

  • Display production reports.

  • Change the name of a felling job.

  • Erase the production reports.

  • Add an operator.

  • Delete an operator.

To enter the "Production" sub-menu, first move the toggle switch on the control panel to the right. This will activate the programming mode. Then press "4" and "ENTER". The display screen is shown in Illustration 1. To enter a sub-menu, press the number key for the sub-menu and then press "ENTER".




Illustration 1g00698249

The production report can be used to print the volumes of the logs. Also, the production report can be used to display the volumes of the logs. The volumes of the logs are measured in cubic meters for the solid measure and the top measure.




Illustration 2g00471380

Measuring Diagram

(1) Solid measure. (2) Top measure. (A) 10 cm (3.9 inch).

Solid measure (1) is the approximate total volume of the log. The volume is the sum of 10 cm (3.9 inch) sections.

Top measure (2) is the volume of the log that is based on the top diameter.

Printout

The "Printout" sub-menu allows you to print the production report for one operator or all operators.

The printout consists of the following values:

  • Total volume for each species in solid measure and top measure

  • Total number of logs for each species

  • The volume of the top measure for each length value in the preselection table

  • The volume of solid measure for each length value in the preselection table

  • The number of logs for each length value in the preselection table

To print the production report, press "1" in the "Production" sub-menu for "Print". Press "ENTER".




Illustration 3g00698261

To print the production report for one operator, press "1". Press "ENTER". Select the desired operator. Press "ENTER".

To print the combined production report for all operators, press "2". Press "ENTER".

Display

The "Display" sub-menu allows you to display the production report for one operator or all operators.

The display consists of the following values:

  • Total volume for each species in solid measure and top measure

  • Total number of logs for each species

  • The volume of top measure for each length value in the preselection table

  • The volume of solid measure for each length value in the preselection table

  • The number of logs for each length value in the preselection table

To display the production report, press "2" in the "Production" sub-menu for "Display". Press "ENTER".




Illustration 4g00698261

To display the production report for one operator, press "1". Press "ENTER". Select the desired operator. Press "ENTER".

To display the combined production report for all operators, press "2". Press "ENTER".

The production report consists of seven screens. The first screen shows the total volume for each species. The volumes are shown for the solid measure and the top measure. Screens 2 and 3 show the volumes of "PINE" for the length values in the preselection table. Screens 4 and 5 show the volumes of "SPRUCE" for the length values in the preselection table. Screens 6 and 7 show the volumes of "HARDWOOD" for the length values in the preselection table.

Press "ESC" in order to return to the main menu.

Felling Number

The "Display" sub-menu allows you to change the name of the felling job. To change the felling number, press "3" in the "Production" sub-menu for "Felling No". Press "ENTER".




Illustration 5g00698293

The felling number can consist of letters and numbers. To enter a letter or a number, press the right arrow key. A list of available letters and numbers will be displayed. Use the right arrow key to highlight a letter or a number. Press "ENTER" in order to select the letter or the number. The keypad can also be used to enter numbers.

After the desired name for felling has been entered, press "ENTER". Press "ESC" in order to return to the main menu.

Resetting

When a felling job has been completed, the current felling job must be erased from the memory. All of the production reports for the current felling job will be deleted so that a new felling job can be created.

To erase the felling job, press "4" in the "Production" sub-menu for "Resetting". Press "ENTER".




Illustration 6g00698298

To delete the production report for one operator, press "1". Press "ENTER". Select the desired operator. Press "ENTER".

To display the combined production report for all operators, press "2". Press "ENTER".




Illustration 7g00698302

Press "ENTER" in order to continue. Press "ESC" in order to end the operation.

The correct code must be entered in order to delete the production report. Enter "007" after "Write Code?" in order to delete the production report.




Illustration 8g00698293

A new name for felling must now be entered. The felling number can consist of letters and numbers.

To enter a letter or a number, press the right arrow key. A list of available letters and numbers will be displayed. Use the right arrow key to highlight a letter or a number. Press "ENTER" in order to select the letter or the number. The keypad can also be used to enter numbers.

After the desired name for felling has been entered, press "ENTER". Press "ESC" in order to return to the main menu.

Operator

The "Operator" sub-menu allows you to change the current operator after the machine has been started. To change the operator, press "5" in the "Production" sub-menu for "Operator". Press "ENTER".

Press the number for the desired operator. Press "ENTER". Press "ESC" in order to return to the main menu.

Note: The current operator can also be selected in the operating mode when the machine is first started.

Change the Name of Operator

Adding, changing, or deleting the name of an operator can be done in the "Change Name of Operator" sub-menu. Press "6" in the "Production" sub-menu. Press "ENTER".

Select the desired number of the operator in order to change or add the name of the operator. Press "ENTER".

An operator's name can consist of letters and numbers. Press the right arrow key in order to enter a letter or a number. A list of available letters and numbers will be displayed. Use the right arrow key to highlight a letter or a number. Press "ENTER" in order to select the letter or the number. The keypad can also be used to enter numbers.

After the desired name of the operator has been entered, press "ENTER". Press "ESC" in order to return to the main menu.

To delete the name of an operator, press "9". Press "ENTER". Select the number for the operator's name that will be deleted. Press "ENTER". Press "ESC" in order to return to the main menu.

Caterpillar Information System:

HH45 Harvester Head, HH55 Harvester Head, HH65 Harvester Head and HH75 Harvester Head Saw Bar - Remove/Install
517 Track-Type Skidder Power Train Final Drive
CP-563D, CS-563D, CS-573D and CS-583D Vibratory Compactors Auxiliary Hydraulic System Auxiliary Hydraulic System
527 Track-Type Skidder Power Train Steering Clutch and Brake
3003, 3013, 3014 and 3024 Engines for Caterpillar Built Machines Fan Drive
793C Off-Highway Truck Machine Systems Air Dryer - Remove and Install
DASA 280 Measuring and Control System Programming Preselections
3406E and 3456 Engines for Caterpillar Built Machines Glossary of Electronic Control Terms
65E, 75E, 85E and 95E Agricultural Tractors Crushing Prevention and Cutting Prevention
793C Off-Highway Truck Machine Systems Solenoid Valve (Air Start) - Remove and Install
3176C and 3196 Engines for Caterpillar Built Machines Basic Engine
3003, 3013, 3014 and 3024 Engines for Caterpillar Built Machines Engine Oil Pump
C15 Petroleum Generator Set Engines Electrical System
IT14G Integrated Toolcarrier and 914G Wheel Loader Machine Systems Quick Coupler - Remove and Install
3003, 3013, 3014 and 3024 Engines for Caterpillar Built Machines Flywheel
517 Track-Type Skidder Power Train Undercarriage
527 Track-Type Skidder Power Train Track Roller Frame
517 Track-Type Skidder Power Train Equalizer Bar
527 Track-Type Skidder Power Train Pivot Shaft
517 Track-Type Skidder Power Train Track Roller
527 Track-Type Skidder Power Train Track Idler
527 Track-Type Skidder Power Train Resonator
3034 Engine for Caterpillar Built Machines Flywheel
793C Off-Highway Truck Machine Systems Double Check Valve (Retarder Control) - Remove and Install
Back to top
The names Caterpillar, John Deere, JD, JCB, Hyundai or any other original equipment manufacturers are registered trademarks of the respective original equipment manufacturers. All names, descriptions, numbers and symbols are used for reference purposes only.
CH-Part.com is in no way associated with any of the manufacturers we have listed. All manufacturer's names and descriptions are for reference only.