CIPI UNDERCARRIAGE Arrangements: 3Q6662, 6Z7861, 6Z7885, 6Z7947, 6Z7957, 6Z7999, 9Q5044, 9Q5065, 9Q5082, 9Q5090, 9Q5093, 9Q5115, 9Q5118, 9Q5126, 9Q5135, 9Q5141, 9Q5168, 9Q5175, 9Q5206, 9Q5255, 9Q5259, 9Q5268, 9Q5412, 9Q5436, 9Q5464, 9Q5514, 9Q5617, 9 Caterpillar


Final Drive - Disassemble

Usage:

OEMS L5E

Type "A" Final Drive Disassembly

Table 1
Required Tools    
Tool     Part Number     Part Description     Qty    
(A)     1P-2420     Transmission Repair Stand     1    
(B)     138-7573     Link Bracket     2    
(C)     1P-1860     Retaining Ring Pliers     1    
(D)     6B-6682     Full Nut     1    
1P-5546 Crossblock     1    
5P-8248 Hard Washer     4    
6V-3142 Puller Plate     1    
 (1) Threaded Rod     1    
 (2) Spacer     4    
(E)     138-7574     Link Bracket     2    
(F)     8B-7561     Step Plate     1    
5F-7465 Puller Assembly     1    
1H-3107 Bearing Puller Assembly     1    
1H-3112 Bearing Puller Assembly     1    
1P-5551 Adjustable Screw Assembly     1    
( 1 ) The 3/4 " - 16 NF threaded rod is 280 mm (11 inch) long.
( 2 ) The spacer's outer diameter is 64 mm (2.5 inch). The spacer's inner diameter is 25.4 mm (1.0 inch). The spacer's thickness is 6.4 mm (.25 inch).

Start By:

  1. Remove the final drive. Refer to Disassembly and Assembly, "Final Drive - Remove" in this manual.

  1. Thoroughly clean the outside of the final drive prior to disassembly.

  1. Put an alignment mark across the sections of the final drive for assembly purposes. The parts must be reinstalled in the part's original locations.



    Illustration 1g00708089

  1. Fasten the final drive to Tooling (A), as shown. The combined weight of the final drive and final drive sprocket is 310 kg (682 lb).

  1. Remove 20 bolts (1) and the washers that hold the cover in position.



    Illustration 2g00708090

  1. Fasten Tooling (B) and a hoist to cover (2), as shown. Remove the cover. The weight of the cover is 32 kg (71 lb).



    Illustration 3g00708091

  1. Remove thrust plate (3) from cover (2) .

  1. Remove two plugs (4) from cover (2) .



    Illustration 4g00708235

  1. Remove O-rings (5) from both plugs (4) that were in the cover.



    Illustration 5g00708092

  1. Remove spacer (6) from carrier assembly (7) .

  1. Remove sun gear (8) from carrier assembly (7) .

  1. Remove carrier assembly (7) by lifting the carrier assembly straight up. The weight of the carrier assembly is 14 kg (31 lb).



    Illustration 6g00708095

  1. Disassemble carrier assembly (7), as follows.

    1. Drive spring pin (10) into planetary shaft (9) with a hammer and a punch.



      Illustration 7g00708144



      Illustration 8g00708218

    1. Remove planetary shaft (9) with spring pin (10) from the carrier assembly.

    1. Remove spring pin (10) from planetary shaft (9) with a hammer and a punch.

    1. Remove two thrust washers (11) and planetary gear (13) from the carrier assembly.

    1. Remove bearing (12) from planetary gear (13) .

  1. Repeat Steps 12.a and 12.e in order to remove the other two planetary gears from the carrier assembly.



    Illustration 9g00708162

  1. Remove sun gear (14) from carrier assembly (15) .



    Illustration 10g00708325

  1. Remove spacer (16) .



    Illustration 11g00708184

    Note: It will be necessary to pry ring gears (17) away from main housing (18) in order to install the lifting slings.

  1. Fasten lifting slings and a hoist to ring gears (17), as shown. Remove the ring gears from main housing (18). The weight of the ring gears is 45 kg (99 lb).



    Illustration 12g00708360

  1. Use a screwdriver or a chisel in order to separate the two ring gears (17) .

    Note: The two ring gears are held together only with 1U-8846 Sealant. It may be necessary to heat the ring gears in order to soften the sealant. Do not heat over 135 °C (275 °F) for more than thirty minutes.




    Illustration 13g00708172

  1. Slide a piece of steel bar stock between the planetary gears in carrier assembly (15), as shown.

  1. Make sure that the bar stock is centered in the carrier assembly. Fasten a lifting sling and a hoist to the steel bar stock, as shown.

  1. Slowly lift carrier assembly (15) from the final drive. The weight of the carrier assembly is 39 kg (86 lb).



    Illustration 14g00708175

  1. Disassemble carrier assembly (15), as follows.

    1. Drive spring pin (20) into planetary shaft (19) with a hammer and a punch.



      Illustration 15g00708370



      Illustration 16g00708220

    1. Remove planetary shaft (19) with spring pin (20) from the carrier assembly.

    1. Remove spring pin (20) from planetary shaft (19) with a hammer and a punch.

    1. Remove two thrust washers (21) and planetary gear (23) from the carrier assembly.

    1. Remove two bearings (22) from the planetary gear.

  1. Repeat Steps 21.a through 21.e in order to remove the other two planetary gears from the carrier.



    Illustration 17g00708186

  1. Remove O-ring seal (24) from main housing (18) .



    Illustration 18g00708187

  1. Remove bolts (25) from gear (26) .



    Illustration 19g00708202

  1. Use Tooling (C) in order to remove gear (26) from main housing (18) .

    Note: The motor housing will separate from the main housing (18). Make sure that the motor housing is supported.




    Illustration 20g00708211

  1. Remove shims (27) from the main housing.



    Illustration 21g00708212

  1. Fasten Tooling (D) and a hoist to main housing (18), as shown.

  1. Use a hammer and a punch in order to separate main housing (18) and the final drive sprocket from the motor housing (28). The combined weight of the main housing and final drive sprocket is approximately 82 kg (181 lb).



    Illustration 22g00708214

  1. Remove Duo-Cone seal (29) from motor housing (28) .

  1. Remove alignment pins (30) .



    Illustration 23g00708215



    Illustration 24g00708216

  1. Remove Duo-Cone seal (31) from main housing (18) .

  1. Use Tooling (E) in order to remove bearings (32) and (33) from the main housing.

  1. If necessary, remove the final drive sprocket from the main housing. Refer to Disassembly and Assembly, "Final Drive Sprocket - Remove and Install" in this manual for the removal of the final drive sprocket from the main housing.

Type "B" Final Drive Disassembly

Table 2
Required Tools    
Tool     Part Number     Part Description     Qty    
(A)     1P-2420     Transmission Repair Stand     1    
(B)     138-7573     Link Bracket     2    
(C)     1P-1860     Retaining Ring Pliers     1    
(D)     6B-6682     Full Nut     1    
1P-5546 Crossblock     1    
5P-8248 Hard Washer     4    
6V-3142 Plate     1    
 (1) Threaded Rod     1    
 (2) Spacer     4    
(E)     138-7574     Link Bracket     2    
(F)     8B-7561     Step Plate     1    
5F-7465 Puller Assembly     1    
1H-3107 Bearing Puller Assembly     1    
1H-3112 Bearing Puller Assembly     1    
1P-5551 Adjustable Screw Assembly     1    
( 1 ) The 3/4" - 16 NF threaded rod is 280 mm (11 inch) long.
( 2 ) The spacer's outer diameter is 64 mm (2.5 inch). The spacer's inner diameter is 25.4 mm (1.0 inch). The spacer's thickness is 6.4 mm (.25 inch).

Start By:

  1. Remove the final drive. Refer to Disassembly and Assembly, "Final Drive - Remove" in this section.

  1. Thoroughly clean the outside of the final drive prior to disassembly.

  1. Put an alignment mark across the sections of the final drive for assembly purposes. The parts must be reinstalled in the part's original locations.



    Illustration 25g00511587

  1. Fasten the final drive to Tool (A), as shown. The combined weight of the final drive and final drive sprocket is 310 kg (683 lb).

  1. Remove 20 bolts (1) and the washers that secure the cover to the final drive.



    Illustration 26g00511600

  1. Use a soft faced hammer and break the seal between cover (2) and the ring gear. Fasten Tool (B) and a hoist to cover (2), as shown. Remove the cover. The weight of the cover is 32 kg (71 lb).



    Illustration 27g00511631

  1. Remove thrust plate (5) from the cover.

  1. Remove 12 socket heads bolts (3) and ring gear (4) from the cover.



    Illustration 28g00511636

  1. Remove sun gear (6). Remove carrier assembly (7) by lifting the carrier assembly straight up. The weight of the carrier assembly is approximately 14 kg (31 lb).



    Illustration 29g00511640



    Illustration 30g00572334

    Note: Two spacers (8) are used with carrier assembly (7). One of the spacers fits on the top side of carrier assembly (7). The other spacer (8) is located in the carrier of carrier assembly (15) .

  1. Remove spacer (8) from carrier assembly (7) .

    Note: Planetary gears (11) might have oil grooves "L". Note the position of the oil grooves in relation to the carrier for assembly purposes.

  1. Remove retaining ring (9) with Tool (C). Remove two thrust washers (10) and planetary gear (11) from the carrier. Remove bearing (12) from the planetary gear.

  1. Repeat Step 10 in order to remove the other two planetary gears from the carrier.



    Illustration 31g00511653

  1. Use a screwdriver, and remove retaining ring (13) from the carrier. Remove sun gear (14) from the carrier.



    Illustration 32g00511661

  1. Use two people in order to remove carrier assembly (15). Remove the carrier assembly by pulling the carrier assembly straight up. The weight of the carrier assembly is approximately 25 kg (55 lb).



    Illustration 33g00511682

    Note: Spacer (16) may remain with carrier assembly (15), or the spacer may remain with carrier assembly (24). Refer to Step 19.

  1. Remove spacer (16) from carrier assembly (15) .



    Illustration 34g00511735



    Illustration 35g00572352

    Note: If spring pin (17) is recessed below the outside surface of the carrier, measure the depth of the spring pin and record this measurement for assembly purposes.

  1. Drive spring pin (17) into planetary shaft (18) with a hammer and a punch.

    Note: Planetary gears (20) might have oil grooves "M". Note the position of the oil grooves in relation to the carrier for assembly purposes.

  1. Remove planetary shaft (18), two thrust washers (19) and planetary gear (20) from the carrier. Remove bearing (21) from the planetary gear. Remove spring pin (17) from planetary shaft (18) with a hammer and a punch.

  1. Repeat Steps 15 and 16 in order to remove the other two planetary gears from the carrier.



    Illustration 36g00511788

  1. Use a screwdriver, and remove retaining ring (22). Remove sun gear (23) from the carrier.



    Illustration 37g00511795

    Typical example

  1. If spacer (16) was not removed in Step 14, remove the spacer from carrier assembly (24) at this time.

  1. Slide a piece of steel bar stock between the planetary gears in carrier assembly (24), as shown. Make sure that the bar stock is centered in the carrier assembly. Fasten a lifting sling and a hoist to the steel bar stock, as shown. Slowly lift carrier assembly (24) from the final drive. The weight of the carrier assembly is approximately 36 kg (80 lb).



    Illustration 38g00511799

    Typical example




    Illustration 39g00572382

    Note: If spring pin (25) is recessed below the outside surface of the carrier, measure the depth of the spring pin and record this measurement for assembly purposes.

  1. Drive spring pin (25) into planetary shaft (26) with a hammer and a punch.

    Note: Planetary gears (28) might have oil grooves "N". Note the position of the oil grooves in relation to the carrier for assembly purposes.

  1. Remove planetary shaft (26), two thrust washers (27) and planetary gear (28) from the carrier. Remove two bearings (29) from the planetary gear. Drive spring pin (25) out of planetary shaft (26) with a hammer and a punch.

  1. Repeat Steps 21 and 22 in order to remove the other planetary gears from the carrier.



    Illustration 40g00511809

    Note: It will be necessary to pry ring gear (30) away from main housing (31) in order to install the lifting slings.

  1. Fasten lifting slings and a hoist to ring gear (30), as shown. Remove the ring gear from main housing (31). The weight of the ring gear is 48 kg (105 lb).



    Illustration 41g00511825

  1. Remove O-ring seal (32) from main housing (31) .



    Illustration 42g00511857

    Typical example




    Illustration 43g00511869

  1. Remove socket head bolts (33) from gear (34) .

  1. Use Tooling (D) to remove gear (34) from the housing.



    Illustration 44g00511872

  1. Remove shims (35) from the housing.



    Illustration 45g00511882

  1. Fasten Tool (E) and a hoist to main housing (31), as shown. Separate the main housing and the final drive sprocket from the motor housing. The combined weight of the main housing and final drive sprocket is 105 kg (231 lb).



    Illustration 46g00511906

  1. Remove Duo-Cone seal (36) from the motor housing.



    Illustration 47g00511934



    Illustration 48g00511939

  1. Remove Duo-Cone seal (37) from the main housing.

  1. Use Tooling (F) to remove bearings (38) and (39) from the main housing.

  1. If necessary, remove the final drive sprocket from the main housing. Refer to Disassembly and Assembly, "Final Drive Sprocket - Remove and Install" in this section for the procedure to remove the final drive sprocket from the main housing.

Caterpillar Information System:

3054 and 3056 Industrial and Generator Set Engines Water Pump
CIPI UNDERCARRIAGE Arrangements: 9Q-5262, 191-4041, and 204-9207 Recoil Spring
3606, 3608, 3612 and 3616 Engines and C280-12, C280-16, C280-6 and C280-8 Marine Engines Standby Pump Panel General Information
2002/01/01 The Procedure For The Disassembly And Assembly Of The Gas Admission Valve Has Been Updated {1250}
3512B Engine for SPF343, SPS343, and SPT343 Pumpers Digital Sensor Supply
Automatic Transfer Switches CTS, CTSD Series Network - Test
CIPI UNDERCARRIAGE Arrangements: 9Q-5262, 191-4041, and 204-9207 Front Idler
Automatic Transfer Switches CTS, CTSD Series Network Card - Configure
Automatic Transfer Switches CTS, CTSD Series Network Card - Replace
3500 Engines for Caterpillar Built Generator Sets Electric Starting Motor
2002/01/01 Corrections to Operation and Maintenance Manual, SEBU6916-04, "3500B Engines and 3500 Engines With EUI Option" , "Maintenance Interval Schedule" {1000, 7500}
3176C and 3196 Engines For Caterpillar Built Machines Housing (Front) - Install
CPT372 Truck Mounted Pumper Engine Oil Level - Check
3054 and 3056 Marine Generator Set Engines Heat Exchanger
3606, 3608, 3612 and 3616 Engines and C280-12, C280-16, C280-6 and C280-8 Marine Engines Standby Pump Panel Contactor - Test
CPT372 Truck Mounted Pumper Power End Oil and Filter - Change
3408E and 3412E Industrial Engines Circuit Breakers
CIPI UNDERCARRIAGE Arrangements: 3Q6662, 6Z7861, 6Z7885, 6Z7947, 6Z7957, 6Z7999, 9Q5044, 9Q5065, 9Q5082, 9Q5090, 9Q5093, 9Q5115, 9Q5118, 9Q5126, 9Q5135, 9Q5141, 9Q5168, 9Q5175, 9Q5206, 9Q5255, 9Q5259, 9Q5268, 9Q5412, 9Q5436, 9Q5464, 9Q5514, 9Q5617, 9 Final Drive - Install
3606, 3608, 3612 and 3616 Engines and C280-12, C280-16, C280-6 and C280-8 Marine Engines Standby Pump Panel Contactor - Adjust
3606, 3608, 3612 and 3616 Engines and C280-12, C280-16, C280-6 and C280-8 Marine Engines Standby Pump Panel Wiring
3408E and 3412E Industrial Engines Muffler
C12 Marine Engine Inlet Manifold Pressure - Test
3500 Industrial Engines Fuel Injector
3408E and 3412E Industrial Engines Air Cleaner
Back to top
The names Caterpillar, John Deere, JD, JCB, Hyundai or any other original equipment manufacturers are registered trademarks of the respective original equipment manufacturers. All names, descriptions, numbers and symbols are used for reference purposes only.
CH-Part.com is in no way associated with any of the manufacturers we have listed. All manufacturer's names and descriptions are for reference only.