Air Cleaner - Remove and Install
Removal Procedure
Show/hide table
Required Tools     | |||
---|---|---|---|
Tool     | Part Number     | Part Description     | Qty     |
A     | 138-7573     | Link Bracket     | 1     |
Start By:
- Install the steering frame lock. Refer to Disassembly and Assembly, "Steering Frame Lock - Remove and Install".
Show/hide table
NOTICE |
---|
Keep all parts clean from contaminants. Contaminants may cause rapid wear and shortened component life. |
- Loosen clamp (2) .
Show/hide table
Illustration 1 | g01082237 |
- Remove three bolts (1) and the washers.
- Remove bolt (3) and the washer. Install Tooling (A) .
- Attach a hoist and a suitable lifting device to Tooling (A). The weight of air cleaner (4) is approximately 48 kg (105 lb).
Show/hide table
Illustration 2 | g01082238 |
- Remove two bolts (5), the nuts and the washers.
- Remove air cleaner (4) from the machine.
Installation Procedure
Show/hide table
Required Tools     | |||
---|---|---|---|
Tool     | Part Number     | Part Description     | Qty     |
A     | 138-7573     | Link Bracket     | 1     |
Show/hide table
NOTICE |
---|
Keep all parts clean from contaminants. Contaminants may cause rapid wear and shortened component life. |
- Attach a hoist and a suitable lifting device to Tooling (A). The weight of air cleaner (4) is approximately 48 kg (105 lb).
Show/hide table
Illustration 3 | g01082238 |
- Position air cleaner (4), as shown.
- Install two bolts (5), the nuts and the washers.
- Install and tighten clamp (2) .
Show/hide table
Illustration 4 | g01082237 |
- Install three bolts (1) and the washers.
- Remove Tooling (A). Install bolt (3) and the washer.
End By: Remove the steering frame lock. Refer to Disassembly and Assembly, "Steering Frame Lock - Remove and Install".
Caterpillar Information System:
R2900G Load Haul Dump Machine Systems Bucket - Remove
AP-800D and BG-230D Asphalt Pavers Machine Systems Truck Hitch
446D Backhoe Loader Power Train Final Drive (Drive and Steering Axle)(Front) - Disassemble - In Chassis
2004/08/02 New Proportional Control Handle Is Now Available {5705}
446D Backhoe Loader Power Train Final Drive (Drive and Steering Axle)(Front) - Remove
446D Backhoe Loader Engine Supplement Hydraulic Oil Cooler - Remove and Install
446D Backhoe Loader Power Train Drive and Steering Axle (Front) - Install
446D Backhoe Loader Power Train Drive and Steering Axle (Front) - Remove
988H Wheel Loader Power Train Engagement Pressure for the Transmission Clutch (Operator Monitor) - Calibrate
2004/07/05 Improved Analysis of Non-Warrantable Failures for Reman Vane Cartridges {5055}
446D Backhoe Loader Power Train Steering Cylinder (Front) - Remove and Install
2004/07/01 Engines Are Now Built with Semi-Crowned Lifter Rollers {1209}
R2900G Load Haul Dump Power Train Differential and Bevel Gear (Front) - Remove
R2900G Load Haul Dump Machine Systems Bucket - Install
2004/07/26 Correction to Disassembly and Assembly, RENR4884 , "Track (Rubber) - Remove and Install - 287B Multi Terrain Loader" {4198}
446D Backhoe Loader Power Train Final Drive (Drive and Steering Axle)(Front) - Assemble - In Chassis
446D Backhoe Loader Power Train Final Drive (Drive and Steering Axle)(Front) - Install
AP-800D and BG-230D Asphalt Pavers Machine Systems Solenoid Valve (Truck Hitch)
988H Wheel Loader Power Train Engagement Pressure for the Lockup Clutch of the Torque Converter (Operator Monitor) - Calibrate
446D Backhoe Loader Power Train Transmission (Power Shift) - Remove
446D Backhoe Loader Power Train Transmission (Power Shift) - Disassemble
446D Backhoe Loader Power Train Transmission (Power Shift) - Assemble
446D Backhoe Loader Power Train Transmission (Power Shift) - Install
770 and 772 Off-Highway Truck Additional Messages