UPSB125 Uninterruptible Power Supply UPS Battery - 50Hz Caterpillar


General Information

Usage:

UPSB 125 SEP

General Description

The 50 Hz battery UPS is a three-phase double conversion uninterruptible power supply (UPS), designed for flexibility to meet a wide range of application requirements.

The 50 Hz battery UPS offers many options to allow for customizing a solution to meet the unique specifications of the customer. The options that are offered include, but are not limited to the following:

  • Adjacent and remote battery cabinets

  • Input and output isolation transformers

  • Options for distribution

  • Parallel system bypass cabinets

  • Variety of communication cards

Description of Information

This manual provides the following information:

  • Detailed 3-dimensional views of system components

  • Troubleshooting

  • Preventive maintenance

  • System checks

  • Testing and Adjusting procedures

  • IGBT replacement procedures

Safety

Ensure that all safety precautions are followed to protect personnel and equipment before performing any operational or service procedures on the UPS.

ReferenceOperations and Maintenance Manual, SEBU8516, "Safety"

Operation and Maintenance Manual

Operation and Maintenance Manual, SEBU8516 contains detailed instruction for the following:

  • Personnel and equipment safety

  • Installation guidelines and procedures

  • Equipment specifications

  • Operating procedures

  • General service procedures

Preventive Maintenance

Always follow the preventive maintenance procedure. The listed preventive maintenance procedures are used to ensure the following:

  • The equipment is serviced uniformly.

  • The equipment is configured properly.

  • The equipment is in proper operating condition.

All preventive maintenance is to be performed only by qualified technicians who have been trained to maintain the product. Preventive maintenance procedures include the following:

Basic Preventive Maintenance - These routines are performed on a minimum of a yearly basis.

Advanced Preventive Maintenance - These routines are performed as needed and for troubleshooting the system.

Complete all maintenance for power distribution equipment that is upstream of the UPS first. Servicing the upstream equipment first will ensure that there will not be any changes to the infrastructure for the power distribution after servicing the UPS.

Before starting these tests, complete the following:

  • Place the upstream disconnects in the ON position. The upstream disconnects are now closed.

  • Ensure that the system is configured to operate in Test Mode.

Test Mode

Test Mode consists of the following:

  • Place the MAINS 1 (Q1) input switch in the ON position. The MAINS 1 input switch is now closed.

  • Place the MAINS 2 (Q4S) input switch in the ON position. The MAINS 2 input switch is now closed.

  • Place the output switch in the ON position. The output switch is now closed.

  • Place the battery disconnects in the ON position. The battery disconnects are now closed.

  • Place the internal maintenance bypass switch in the OFF position. The internal maintenance bypass switch is now open.

If any conditions do not occur, troubleshoot the fault and correct the issue. Verify that the operations and alarm functions of the UPS are correct.

Caterpillar Information System:

TA19 Transmission Speed Sensor (Transmission Input) - Remove and Install
Cat® Grade Control Depth & Slope for E-Series and F-Series Excavators End User License Agreement
TA19 Transmission Speed Sensor (Transmission Output) - Remove and Install
3516C Generator Sets Fuel Injector - Inspect/Adjust
330F MHPU Mobile Hydraulic Power Unit Machine System Control Valve (Boom Lowering) - Manual
C9 Industrial Engines Product Description
TA19 Transmission Temperature Sensor (Transmission Oil) - Remove and Install
C15 Petroleum Engines Cat Data Link - Test
320E and 323E Excavators Equipment Lowering with Engine Stopped
C18 Marine Engine Cooling System - Test
C3.4B Industrial Engine Fuel System Primary Filter/Water Separator - Drain
C3.4B Industrial Engine Fuel System - Prime
UPSB125 Uninterruptible Power Supply UPS Battery - 50Hz Component Location
UPSB125 Uninterruptible Power Supply UPS Battery - 50Hz IGBT for CSIEN-CSION-CSPEN Circuit Board - Replace
UPSB125 Uninterruptible Power Supply UPS Battery - 50Hz IGBT for CSNEN-CSNON Circuit Board - Replace
UPSB125 Uninterruptible Power Supply UPS Battery - 50Hz IGBT for DCHEN-DCHON Circuit Board - Replace
UPSB125 Uninterruptible Power Supply UPS Battery - 50Hz IGBT for MUTEN-MUTON Circuit Board - Replace
C9 Industrial Engines Product Lifting
UPSB125 Uninterruptible Power Supply UPS Battery - 50Hz IGBT - Test
Installation Procedure for 374-5523 Stick Lines Gp on Certain Hydraulic Excavators {5057} Installation Procedure for 374-5523 Stick Lines Gp on Certain Hydraulic Excavators {5057}
TA19 Transmission Pressure Sensor (Transmission Oil) - Remove and Install
146-4080 Digital Multimeter Specification, Testing, and Maintenance Manual{0374, 0599, 0709} 146-4080 Digital Multimeter Specification, Testing, and Maintenance Manual{0374, 0599, 0709}
C9 Industrial Engines Engine Oil and Filter - Change
C9 Industrial Engines Fuel System - Prime
Back to top
The names Caterpillar, John Deere, JD, JCB, Hyundai or any other original equipment manufacturers are registered trademarks of the respective original equipment manufacturers. All names, descriptions, numbers and symbols are used for reference purposes only.
CH-Part.com is in no way associated with any of the manufacturers we have listed. All manufacturer's names and descriptions are for reference only.