Final Drive Planetary Carrier (In Chassis) - Install - Right and Left Side
Installation Procedure
Show/hide table
Required Tools     | |||
Tool     | Part Number     | Description     | Qty     |
A     | 1P-0068     | Cone     | 1     |
1P-0069 | Head     | 1     | |
1P-0071 | Jaw     | 3     | |
8K-8466 | Stud     | 1     | |
1A-8285 | Nut     | 3     | |
6H-0187 | Bolt     | 3     | |
1P-5546 | Block     | 1     | |
5P-8247 | Washer     | 1     | |
1B-4206 | Nut     | 1     | |
B     | 3B-2968     | Bolt     | 3     |
C     | 5P-8622     | Shackle     | 1     |
8T-3207 | Lifting Bracket     | 1     | |
1A-8063 | Bolt     | 2     | |
5P-8248 | Washer     | 6     | |
1B-4331 | Nut     | 2     | |
D     | 1P-0520     | Driver Gp     | 1     |
E     | 5P-0960     | Grease Cartridge     | 1     |
Show/hide table
NOTICE |
---|
Care must be taken to ensure that fluids are contained during performance of inspection, maintenance, testing, adjusting and repair of the product. Be prepared to collect the fluid with suitable containers before opening any compartment or disassembling any component containing fluids. Refer to Special Publication, NENG2500, "Caterpillar Tools and Shop Products Guide" for tools and supplies suitable to collect and contain fluids on Caterpillar products. Dispose of all fluids according to local regulations and mandates. |
- Use Tooling (D) in order to install lip seal (10). Install lip seal (10) so that the lip of the seal faces the inside of the hub.
Note: Lubricate lip seal (10) with the lubricant that is being sealed.
Show/hide table
Illustration 1 | g01239424 |
- Apply Tooling (E) to the back side of thrust ring (9) in order to hold thrust ring (9) in place. Install thrust ring (9) .
Show/hide table
Illustration 2 | g01239422 |
- Adjust Tooling (C) so that Dimension (X) measures 145 mm (5.7 inch). Install Tooling (C) to planetary carrier (4) and attach a suitable lifting device to Tooling (C). The weight of planetary carrier (4) is approximately 209 kg (461 lb). Position planetary carrier (4). Install sun gear (6) to planetary carrier (4). Install Tooling (A) in order to hold sun gear (6) in place.
Show/hide table
Illustration 3 | g01239417 |
Show/hide table
Illustration 4 | g01239406 |
- Install O-ring seals (8) and (7) .
- Align the gears in planetary carrier (4) and push planetary carrier (4) into the hub until planetary carrier (4) is 25 mm (1.0 inch) from the hub. Install Tooling (B) .
Note: Tooling (B) must be installed to a depth of 25 mm (1.0 inch) in order to hold planetary carrier (4) .
Show/hide table
Illustration 5 | g01239495 |
- Install bolts (5). Tighten bolts (5) to a torque of 430 ± 60 N·m (317 ± 44 lb ft). Remove Tooling (B). Install remaining bolts (5) .
- Remove Tooling (C) .
- Install the outer axle. Refer to Disassembly and Assembly, "Axle - Install".
- Install drain plug (11) and the O-ring seal. Fill the final drive with oil. Refer to Operation and Maintenance Manual, "Final Drive Oil Level - Check".
- Refer to Steps 1 through 9 for the planetary carrier on the opposite side of the machine.
- The following procedure is for the left side of the machine.
- Use a suitable lifting device in order to position ladder assembly (2) to the original position. The weight of ladder assembly (2) is approximately 27 kg (60 lb). Install bolts (3), the washers, and clamps (1) .
Show/hide tableIllustration 6 g01239293
- The following procedure is for the right side of the machine.
- Raise the counterweight. Refer to Operation and Maintenance Manual, "Counterweight Control" for the correct procedure.
Caterpillar Information System:
24M Motor Grader Machine Systems Battery
C15 and C18 Generator Set Engines Housing (Front) - Remove
CD54 Paving Compactor Fuses - Replace
AS2302 Vers-A-Mat Asphalt Screed Screed Extensions
AS2302 Vers-A-Mat Asphalt Screed Screed Heat Control
583T Pipelayer Power Train Final Drive Planetary Carrier (In Chassis) - Remove - Right and Left Side
C15 and C18 Generator Set Engines Gear Group (Front) - Install
583T Pipelayer Power Train Final Drive - Install - Right and Left Side
24M Motor Grader Power Train Torque Converter
M325D and M330D Excavators Power Train Electronic Control System MID 027 - CID 0298 - FMI 03
Clarification of Vertical Method Configuration in GPS/ATS AccuGrade TM Version 6.0 Software Operation for Motor Graders {7220} Clarification of Vertical Method Configuration in GPS/ATS AccuGrade TM Version 6.0 Software Operation for Motor Graders {7220}
587R Pipelayer Cooling System Coolant Extender (ELC) - Add
C15 and C18 Generator Set Engines Housing (Front) - Install
2006/02/13 New Hood Hinge Pins for Medium Wheel Loaders {7251}
2006/02/13 Change to Fan Shroud Increases Clearance {1353, 7272}
587R Pipelayer Towing the Machine
R1700G Load Haul Dump Machine Systems Tilt Cylinder - Remove
R1700G Load Haul Dump Power Train Axle Shaft - Remove
R1700G Load Haul Dump Power Train Trunnion Support (Oscillating Axle, Rear) - Install
C4.4 and C6.6 Industrial Engines and Engines for Caterpillar Built Machines CID 0005 FMI 02
C4.4 and C6.6 Industrial Engines and Engines for Caterpillar Built Machines CID 0005 FMI 05
C4.4 and C6.6 Industrial Engines and Engines for Caterpillar Built Machines CID 0005 FMI 06
C4.4 and C6.6 Industrial Engines and Engines for Caterpillar Built Machines CID 0005 FMI 07
C4.4 and C6.6 Industrial Engines and Engines for Caterpillar Built Machines CID 0006 FMI 02