Fuel Ratio Control - Disassemble
Disassembly Procedure
Show/hide table
Required Tools     | |||
---|---|---|---|
Tool     | Part Number     | Description     | Qty     |
A     | FT-1820     | Fixture Assembly     | 1     |
B     | 1P-1855     | Retaining Ring Pliers     | 1     |
C     | 6V-9072     | Piston Seal Guide     | 1     |
Start By:
- Remove the fuel ratio control. Refer to Disassembly and Assembly, "Fuel Ratio Control - Removal".
- Put Tool (A) in a vise so that the station that is being used is not over the jaw of the vise.
Show/hide table
Illustration 1 | g00496767 |
- Remove bolts (6). Remove cover (7) from housing (10) .
Show/hide table
Personal injury can result from parts and/or covers under spring pressure. Spring force will be released when covers are removed. Be prepared to hold spring loaded covers as the bolts are loosened. |
- Remove nut (5) and stop (4) from cover (7) .
- Remove spring (8), washer (9) and diaphragm (21) from retainer (25). Remove retainer (25) from housing (10) .
- Remove tube (1) from the end of extension (19). Remove nut (2) from extension (19) and remove the extension from retainer (25). Remove valve (16), spring (22) and O-ring seal (23) from the extension.
- Remove spring (20), retainer (18) and spring (17) from housing (10) .
- Remove piston (12) and valve assembly (14) from the housing.
- Use Tool (B) and remove snap ring (13) and washer (15) from the valve assembly. Remove piston (12) from the valve assembly.
- Remove seal (11) from piston (12) .
- Remove the stem portion from valve assembly (14), if necessary.
- Clean all of the parts and inspect the parts. Make a replacement for all of the parts that are worn or damaged.
Caterpillar Information System:
3304B and 3306B Engines for Caterpillar Built Machines Flywheel - Install
583R Pipelayer Engine Supplement Fuel Ratio Control - Install
784C and 785C Off-Highway Truck/Tractors Air System and Brakes Control Valve (Pulled Unit)
583R Pipelayer Engine Supplement Fuel Ratio Control - Remove
IT14G Integrated Toolcarrier and 914G Wheel Loader Machine Systems Gear Pump (Implement, Steering and Brakes) - Disassemble
583R Pipelayer Engine Supplement Fuel Filter and Base - Remove and Install
3406E and 3456 Engines for Caterpillar Built Machines Engine Oil Cooler - Install
784C and 785C Off-Highway Trucks Machine Systems Steering Accumulator - Install
784C and 785C Off-Highway Truck/Tractors Air System and Brakes Hydraulic Tank (Torque Converter, Pulled Unit, Brake, and Transmission)
784C and 785C Off-Highway Truck/Tractors Air System and Brakes Hydraulic Tank (Torque Converter, Hoist, Brake and Transmission)
769D Off-Highway Truck and 771D Quarry Truck Access and Exit Procedures
3306C Engines for Caterpillar Built Machines Cylinder Block
3304B and 3306B Engines for Caterpillar Built Machines Pistons and Connecting Rods - Remove
3406E On-Highway Engine Engine Oil Filter Base - Install
583R Pipelayer Power Train Idler - Remove
583R Pipelayer Engine Supplement Fuel Ratio Control - Assemble
CB-534C Vibratory Compactor Before Starting Engine
784C and 785C Off-Highway Trucks Machine Systems Solenoid and Relief Valve (Steering) - Remove
3306C Engines for Caterpillar Built Machines Piston Cooling Jet
583R Pipelayer Engine Supplement Fuel Transfer Pump - Remove
784C, 785C, 785D, 789C, 789D, 793C and 793D Off-Highway Trucks Power Train Electronic Control System Relays
IT14G Integrated Toolcarrier and 914G Wheel Loader Power Train System Pressure - Release
583R Pipelayer Engine Supplement Fuel Transfer Pump - Install
784C, 785C, 785D, 789C, 789D, 793C and 793D Off-Highway Trucks Power Train Electronic Control System Switches