- Wheel Loader:
- 950G (S/N: 3JW1-UP; 5MW1-UP; 5FW1-UP; 8JW1-UP)
- Wheel Loader:
- 962G (S/N: 4PW1-UP; 6EW1-UP; 7BW1-UP; 6HW1-UP)
- Wheel Loader:
- 966G (S/N: 3SW1-UP; 3PW1-UP; 8XW1-UP)
- Wheel Loader:
- 972G (S/N: 4WW1-UP; 6AW1-UP; 9GW1-UP)
- Integrated Toolcarrier:
- IT62G (S/N: AKP1-UP; 6PS1-UP)
Earlier Wheel Loader and Integrated Toolcarrier models require a separate procedure for replacement of the transmission control group.
Refer to the table below for the serial number breaks on the models that are affected. For further information on the connection, refer to the schematics that are referenced in the table below.
Sales Model     | Early Production     | Later Production     | ||
Serial Number Range | Schematic     | Serial Number Range     | Schematic     | |
950G     | S/N:3JW1-2153     | SENR1393     | S/N:3JW2154-UP     | RENR4328     |
S/N:5MW1-1077 | S/N:5MW1078-UP | |||
S/N:5FW1-1999 | S/N:5FW2000-UP | |||
S/N:8JW1-406 | S/N:8JW407-UP | |||
962G     | S/N:4PW1-503     | S/N:4PW504-UP | ||
S/N:6EW1-799 | S/N:6EW500-UP | |||
S/N:7BW1-623 | S/N:7BW624-UP | |||
S/N:6HW1-414 | S/N:6HW415-UP | |||
IT62G     | S/N:AKP1-513     | S/N:AKP514-UP | ||
S/N:6PS1-UP | - | -     | ||
966G     | S/N:3SW1-1224     | RENR2118     | S/N:3SW1225-UP     | RENR4375     |
S/N:3PW1-1099 | S/N:3PW1100-UP | |||
S/N:8XW1-755 | S/N:8XW756-UP | |||
972G     | S/N:4WW1-719     | S/N:4WW720-UP | ||
S/N:6AW1-499 | S/N:6AW500-UP | |||
S/N:9GW1-507 | S/N:9GW508-UP |
Replacement of the transmission control group for the earlier models that are listed requires the following procedure.
Illustration 1 | g01154758 |
Original 154-8261 Transmission Control Group (1) 139-4702 Transmission Control (2) 9X-6615 Bolt (3) 154-6743 Bracket (4) 148-9267 Control Harness |
Illustration 2 | g01161231 |
Schematic for earlier models |
Turn the ignition key to the OFF position. Turn the battery disconnect switch to the OFF position. Remove wire 322-GY from pin location 2 of 148-9267 Control Harness (4). Disconnect 148-9267 Control Harness (4) from the cab harness. The 148-9267 Control Harness will not be reused for reconnection of the transmission control group.
Illustration 3 | g01161255 |
Replacement 121-9300 Transmission Control Group (5) 201-0212 Transmission Control (6) 134-1374 Bolt (7) 322-GY Wire from horn switch |
Illustration 4 | g01161242 |
Schematic for later models |
Install wire 322-GY (7) to pin location 2 on the new 12-pin connector on 201-0212 Transmission Control (5) .
Remove 154-6743 Bracket (3) and four 9X-6615 Bolts (2). Mount 201-0212 Transmission Control (5) to the column with four 134-1374 Bolts (6) .
Plug the harness that is attached to the new transmission control into the cab harness. Properly secure the harness in order to prevent rubbing or pinching. Operate the machine in all gears in order to confirm proper operation of the shifter.