Usage:

All Caterpillar Diesel Engines with Either a 12 Volt or 24 Volt Electrical System

Introduction

Depending on the voltage of the engine electrical system, one of the fuel boost pump groups given above can be installed for use on a specific engine. Installation of a fuel boost pump will assist the standard fuel transfer pump, and give better fuel delivery in those instances where it is needed. A primary fuel filter is included in the fuel boost pump group, and must also be installed. Use the following procedure to install the fuel boost pump group.

Installation of Fuel Boost Pump Group

The above schematic shows the location of fuel system parts after installation of the fuel boost pump group is complete.

Parts shown in the schematic are as follows: 1. Fuel supply tank. 2. Primary fuel filter. 3. Fuel boost pump. 4. Mounting clips (two). 5. Water separator. 6. Fuel filter (existing). 7. Fuel injection pump and governor. 8. Fuel boost pump ground wire (black). 9. Fuel boost pump power supply wire (brown).

NOTE: Install the primary fuel filter and the fuel boost pump as near as possible to fuel supply tank (1).

1. Disconnect the battery and shut off the fuel supply to the engine.

2. Install 7W7831 Primary Fuel Filter (2) in a location that will provide for easy access when filter service is required. Be sure to install primary filter (2) so the IN port is toward the fuel supply tank.

NOTE: The IN and OUT ports in the filter base of primary fuel filter (2) are straight thread O-ring for No.8 port, with 3/4"-16 threads.

3. Install fuel boost pump (3) on a good solid surface that does not have, or cause, a vibration. The fuel boost pump must be installed in a location where it will not be damaged by too much water, or any other foreign material.

4. Fuel boost pump (3) must, also, be installed in a location that is not more than 610 mm (24.0") above the bottom of fuel supply tank (1). The IN port of fuel boost pump (3) must be toward primary fuel filter (2).

5. Use mounting clips (4) to fasten fuel boost pump (3) securely in position.

NOTE: The IN and OUT ports of fuel boost pump (3) have 1/4"-18 threads for fuel line connections.

6. Install and connect the fuel line from fuel supply tank (1) to primary fuel filter (2), then connect the fuel line from primary fuel filter (2) to fuel boost pump (3).

7. Now, connect a fuel line from fuel boost pump (3) to water separator (5). Connect the fuel line from water separator (5) to existing fuel filter (6), and then from existing fuel filter (6) to fuel injection pump and governor (7).

8. The black electrical wire (8) is the ground wire. Clean all paint and rust from the location where the ground wire is to be connected to the machine. Use 16 gauge electrical wire for the ground connection.

9. The brown electrical wire (9) is for the power supply connection, and must be connected as follows:

* If the fuel boost pump is to operate constantly while the engine is in operation, connect brown power supply wire (9) to a power source that is energized only when the engine is in operation.
* If constant operation of the fuel boost pump is not needed, install an ON-OFF switch between the power source and brown power supply wire (9).

NOTE: This fuel boost pump is grounded internally, and must be switched on the power supply side.

* Use 16 gauge electrical wire for the power supply connection.

10. After installation of the fuel boost pump group is complete, turn on the fuel supply and connect the battery.

11. Start the engine and check for fuel leaks. Make repairs if necessary.

Caterpillar Information System:

Installation of Hydraulic Tank{5056} Installation of Hydraulic Tank{5056}
Installation of D7H "S" Bulldozer (4T2434) Spill Plates{6051} Installation of D7H "S" Bulldozer (4T2434) Spill Plates{6051}
Installation of 10S (1RH) and 10U (1SH) Bulldozer{6051, 6053} Installation of 10S (1RH) and 10U (1SH) Bulldozer{6051, 6053}
Installation of No. 10 Ripper (1WH, 1XH){6311, 6312} Installation of No. 10 Ripper (1WH, 1XH){6311, 6312}
Installation of D7H "Su" Bulldozer (3G5435) Spill Plates{6078} Installation of D7H "Su" Bulldozer (3G5435) Spill Plates{6078}
Installation of No. 8 Ripper (1FH){6311} Installation of No. 8 Ripper (1FH){6311}
Installation of 8SU (1KH) and 8U (1JH) Bulldozers{6051, 6053} Installation of 8SU (1KH) and 8U (1JH) Bulldozers{6051, 6053}
Installation of 9SU (7NH) and 9U (7PH) Bulldozers{6078, 6053} Installation of 9SU (7NH) and 9U (7PH) Bulldozers{6078, 6053}
Installation of No. 9 Ripper (1NH, 1PH){6311, 6312} Installation of No. 9 Ripper (1NH, 1PH){6311, 6312}
Installation of 935B Governor Control Conversion Kit 8Y0156{1265} Installation of 935B Governor Control Conversion Kit 8Y0156{1265}
Procedure for Repairing/Improving Scraper Retarder and Transfer Gear Group{3117} Procedure for Repairing/Improving Scraper Retarder and Transfer Gear Group{3117}
Radiator Grill Modification to Install Light Group{1381, 7309} Radiator Grill Modification to Install Light Group{1381, 7309}
Installation of D6H Bulldozer (1U1274, 4T1533, 9W3092) Spill Plates{6078} Installation of D6H Bulldozer (1U1274, 4T1533, 9W3092) Spill Plates{6078}
Adjustable Arm Rest for D4H and D5H Tractors{7300} Adjustable Arm Rest for D4H and D5H Tractors{7300}
Reconditioning Ripper Pin Bores{6310, 6311, 6312, 6313, 6314, 6315, 6316} Reconditioning Ripper Pin Bores{6310, 6311, 6312, 6313, 6314, 6315, 6316}
Using the Digital Diagnostic Tool (DDT) NEXG4511 Industrial Engine Service Program Module{0781, 0782} Using the Digital Diagnostic Tool (DDT) NEXG4511 Industrial Engine Service Program Module{0781, 0782}
Installation of 8A (1HH) Bulldozer{6052} Installation of 8A (1HH) Bulldozer{6052}
Procedure For Welding J-Series Flush Mount, Bottom Strap, And Two Strap Adapters To Bucket Base Edges{6803} Procedure For Welding J-Series Flush Mount, Bottom Strap, And Two Strap Adapters To Bucket Base Edges{6803}
Installation of Unishaft Drive Line{3253} Installation of Unishaft Drive Line{3253}
Installation of 1U5495 Latch Group on Large Duo-Cone Seal Installers{0600, 0700, 7561} Installation of 1U5495 Latch Group on Large Duo-Cone Seal Installers{0600, 0700, 7561}
Speed Reducer Retrofit{6236} Speed Reducer Retrofit{6236}
2T1725 Implement Valve Conversion{6201, 5321} 2T1725 Implement Valve Conversion{6201, 5321}
Installation of Swing-Out Windshield{7310} Installation of Swing-Out Windshield{7310}
Installation of Ladder Assembly{7254} Installation of Ladder Assembly{7254}
Back to top
The names Caterpillar, John Deere, JD, JCB, Hyundai or any other original equipment manufacturers are registered trademarks of the respective original equipment manufacturers. All names, descriptions, numbers and symbols are used for reference purposes only.
CH-Part.com is in no way associated with any of the manufacturers we have listed. All manufacturer's names and descriptions are for reference only.