R1700G Load Haul Dump Machine Systems Caterpillar


Ejector Bucket - Assemble

Usage:

R1700G SBR

Assembly Procedure

Table 1
Required Tools    
Tool     Part Number     Part Description     Qty    
A     304-6261     Support     2    
C     1U-9201     Lever Puller Hoist     1    
D     138-7574     Link Bracket     2    
J     -     Loctite C5-A     -    
K     1P-1839     Bearing Puller Adapter     1    
L     1P-0520     Driver Gp     1    
M     -     Cat Advanced 3 Moly Grease     -    

Note: Check the O-ring seals, the gaskets, and the seals for wear or for damage. Replace the components, if necessary.

Note: Ensure that the pin bores in the ejector bucket, lift arm assembly and tilt link are free of dirt and debris.




    Illustration 1g01402320

  1. Apply Tooling (M) to the bore of ejector cylinder (1) .

  1. Attach a suitable lifting device to ejector cylinder (1). The weight of the ejector cylinder is approximately 52 kg (115 lb).

  1. Install ejector cylinder (1) to the ejector bucket. Align the bores of the ejector cylinder and the ejector bucket.

  1. Install the ejector cylinder pin and shims.



    Illustration 2g01102509

  1. Install three caps (21) .



    Illustration 3g01102511

  1. Install three bungs (22) .

  1. Apply Tooling (J) to the inside diameter and the outside diameter of the collets.



    Illustration 4g01102517

    Typical example

  1. Install collet (20) .

  1. Install the collet on the other side.



    Illustration 5g01193250

  1. Apply Tooling (J) to the threads of bolt (19) prior to assembly. Install bolt (19) and the washer.

    Note: The collet on one side must not extend farther than the other when the bolt is tight.

  1. Tighten bolt (19) to a torque of 370 ± 50 N·m (275 ± 37 lb ft). After the bolt is tight, hit collet (20) on each side with a heavy hammer until the torque on the bolt is less than 200 N·m (150 lb ft).

  1. Tighten bolt (19) again to a torque of 370 ± 50 N·m (275 ± 37 lb ft). Hit each collet again until the torque for the bolt is less than 285 N·m (210 lb ft).

  1. Tighten bolt (19) to a final torque of 370 ± 50 N·m (275 ± 37 lb ft).

    Note: At the end of 50 service hours, repeat Step 11 through Step 13.




    Illustration 6g01402296

  1. Install Tooling (A) in order to support ejector cylinder (1) in the horizontal position.

  1. Install clip (17) .

  1. Connect hose assemblies (15), (16) and (18) .

  1. Repeat Step 1 through Step 16 for the other ejector cylinder.



    Illustration 7g01338657

  1. Lower the temperature of bearing (14) to −75° ± 5°C (−103° ± 9°F). Use Tooling (K) to install bearing (14) to a depth of 9.5 ± 1 mm (0.37 ± 0.04 inch) below the surface of the bore.

  1. Use Tooling (L) to install lip seal (13). Install lip seal (13) with the sealing lip towards the outside of the main ejector plate assembly.

  1. Repeat Step 18 and Step 19 for the other side of the main ejector plate assembly.



    Illustration 8g01338656

  1. Attach a suitable lifting device to lower ejector plate assembly (11). The weight of lower ejector plate assembly (11) is approximately 175 kg (385 lb).

  1. Apply Tooling (J) to the bores of lower ejector plate assembly (11) and main ejector plate assembly (7) .

  1. Align the bores of lower ejector plate assembly (11) and main ejector plate assembly (7) .

  1. Use two people to install the hinge pin. The weight of the hinge pin is approximately 25 kg (55 lb).

  1. Apply Tooling (J) to the threads of bolts (12) prior to assembly.

  1. Install two bolts (12), and the washers. Tighten bolts (12) to a torque of 430 ± 60 N·m (315 ± 45 lb ft).



    Illustration 9g01429058

  1. Install Tooling (C), Tooling (D) and, a suitable lifting device to ejector plate (7). The weight of the main ejector plate assembly with the lower ejector plate assembly attached is approximately 1275 kg (2810 lb).



    Illustration 10g01338655

  1. Apply Tooling (M) to the bores of the ejector bucket and the bores of the main ejector plate assembly.

  1. Align the bores of the ejector bucket with the bores of the main ejector plate assembly.

  1. Install shims (10) (not shown) as required between the ejector bucket and the main ejector plate assembly.

  1. Install pin (9) .

  1. Apply Tooling (J) to the threads of bolt (8) prior to assembly.

  1. Install bolt (8), and the washer.

  1. Repeat Step 30 through Step 33 for the other side of the ejector bucket.



    Illustration 11g01338651

    Typical example

  1. Apply Tooling (M) to the bore of the ejector cylinder.

  1. Align the bores of the main ejector plate assembly with the bore of the ejector cylinder.

  1. Install shims (5) as required.

  1. Install pin (6) .



    Illustration 12g01103423

  1. Install three caps (23) to the collets.



    Illustration 13g01103424

  1. Install three bungs (24) to the collets.



    Illustration 14g01338648

    Typical example

  1. Apply Tooling (J) to the inside diameter and the outside diameter of the collets.

  1. Install collet (4). Install the collet to the other side.

  1. Apply Tooling (J) to the threads of bolt (3) .

  1. Install bolt (3) and the washer.

    Note: The collet on one side must not extend farther than the other when the bolt is tight.

  1. Tighten bolt (3) to a torque of 370 ± 50 N·m (275 ± 37 lb ft). After the bolt is tight, hit the collet on each side with a heavy hammer until the torque on the bolt is less than 200 N·m (150 lb ft).

  1. Tighten bolt (3) again to a torque of 370 ± 50 N·m (275 ± 37 lb ft). Hit each collet again until the torque for the bolt is less than 285 N·m (210 lb ft).

  1. Tighten bolt (3) to a final torque of 370 ± 50 N·m (275 ± 37 lb ft).

    Note: At the end of 50 service hours, repeat Step 45 through Step 47.

  1. Install cover plate (2) .



    Illustration 15g01338208

    Rear view of the ejector bucket

  1. Remove Tooling (A) from ejector cylinder (1) .

  1. Repeat Step 35 through Step 49 for the other ejector cylinder.

  1. Lubricate the ejector cylinder bearings. Refer to Operation and Maintenance Manual, "Ejector Cylinder Bearings - Lubricate".

  1. Lubricate the main ejector plate assembly bearings. Refer to Operation and Maintenance Manual, "Ejector Plate Bearings - Lubricate".

  1. Fill the hydraulic tank with oil to the correct level. Refer to Operation and Maintenance Manual, "Hydraulic System Oil Level - Check".

End By: Remove the steering frame lock. Refer to Disassembly and Assembly, "Steering Frame Lock - Remove and Install".

Caterpillar Information System:

R1700G Load Haul Dump Machine Systems Ejector Bucket - Disassemble
RM-300 Reclaimer Mixer Machine Systems Rotor Stub Shaft - Disassemble
R1700G Load Haul Dump C11 Engine Supplement Exhaust Purifier and Muffler - Install
572R Series 2, 583T, 587T, PL83 and PL87 Pipelayers Transmission - 583T PL83 587T And PL87
Clarification of Lift + Cross Slope Configuration in GPS/ATS AccuGrade TM Version 6.0 Software Operation for Motor Graders {7220} Clarification of Lift + Cross Slope Configuration in GPS/ATS AccuGrade TM Version 6.0 Software Operation for Motor Graders {7220}
572R Series 2, 583T, 587T, PL83 and PL87 Pipelayers Implement System - 583T 587T PL83 And PL87
RM-300 Reclaimer Mixer Machine Systems Chain Drive (Rotor) - Remove and Install
C7 Engine for 584 and 584HD Forwarders and for 525C, 535C, and 545C Wheel Skidders Throttle Position Sensor Circuit - Test
C15 and C18 Generator Set Engines Crankshaft Front Seal - Install
777F Off-Highway Truck Hydraulic System Hydraulic and Transmission Tank (Torque Converter, Hoist, Brake)
RM-300 Reclaimer Mixer Machine Systems Oil Tank (Rotor Drive Lubrication) - Remove and Install
2006/03/20 Three Seal Installers Available for Servicing Hand Metering Units {0732, 4312}
R1700G Load Haul Dump C11 Engine Supplement Hood - Remove
2006/02/13 Barrel Adapter Allows Technician to Attach Filter Unit to Barrel {0645, 0680}
R1700G Load Haul Dump Power Train Axle Shaft - Install
M325D L MH and M325D MH Material Handlers Hydraulic System Relief Valve (Pilot) - Test and Adjust
587R Pipelayer Power Train Troubleshooting
24M Motor Grader Power Train Output Transfer Gear and Case
24M Motor Grader Machine Systems Circle
AS2302 Vers-A-Mat Asphalt Screed Specifications
AS2302 Vers-A-Mat Asphalt Screed Plate Locations and Film Locations
C15 and C18 Generator Set Engines Front Cover - Remove
C15 and C18 Generator Set Engines Front Cover - Install
C15 and C18 Generator Set Engines Gear Group (Front) - Remove
Back to top
The names Caterpillar, John Deere, JD, JCB, Hyundai or any other original equipment manufacturers are registered trademarks of the respective original equipment manufacturers. All names, descriptions, numbers and symbols are used for reference purposes only.
CH-Part.com is in no way associated with any of the manufacturers we have listed. All manufacturer's names and descriptions are for reference only.