D250E Series II and D300E Series II Articulated Trucks Machine Systems Caterpillar


Hoist Control Valve - Assemble

Usage:

D250E II 4PS

Assembly Procedure

Table 1
Required Tools 
Tool  Part Number  Part Description  Qty 
A  1P-0510  Driver Group 

  1. Inspect all parts and clean all parts. If any parts are worn or damaged, use new Caterpillar parts for replacement.


    Illustration 1g00480983

  2. Install O-ring seals (98) to test ports (92). Install caps (97) to test ports (92).


    Illustration 2g00497586

  3. Install valve (94), spring (95) and O-ring seal (96) to plug (91).


    Illustration 3g00480840

  4. Install plug (91), the spring and the valve to the valve body. Install the O-ring seal to plug (93). Install two test ports (92) and plug (93) to the valve body.


    Illustration 4g00497448

  5. Install valve (90) to valve body (81). Install O-ring seal (88) and O-ring seal (89) to valve body (81).


    Illustration 5g00497449
    This assembly is a component of valve assembly (69).

  6. Install nut (82), washer (86), two O-ring seals (85) to valve assembly (83) and valve housing (84). Install valve assembly (83) to valve housing (84). Install retaining ring (87) to valve assembly (83).


    Illustration 6g00497444
    This assembly is a component of valve assembly (69).

  7. Install valve housing (81) to valve assembly (80).


    Illustration 7g00497445


    Illustration 8g00578741

  8. Install valve assembly (69) to valve body (3). Valve assembly (69) will need to be adjusted after the hoist control valve is installed. For instructions on adjustment of the valve, refer to Testing and adjusting, RENR3400.


    Illustration 9g00480609
    This assembly is a component of valve assembly (68).

  9. Install spring (75), plate (74) , valve (73), O-ring seal (71) and O-ring seal (70) to valve assembly (72).

  10. Install nut (77), O-ring seal (76) and washer (78) to retainer assembly (79). Install retainer assembly (79) to valve assembly (72).


    Illustration 10g00573437

  11. Install valve assembly (68) to valve body (3). Valve assembly (68) will need to be adjusted after the hoist control valve is installed. For instructions on adjustment of the valve, refer to Testing and adjusting, RENR3400.


    Illustration 11g00498330


    Illustration 12g00497580
    This assembly is a component of valve assembly (53).

  12. Use Tooling (A) and a hydraulic press in order to install seat (67), spring (66) and valve (65) to valve body (60).


    Illustration 13g00480588
    This assembly is a component of valve assembly (53).

  13. Install nut (58) and retainer assembly (64) to cap assembly (57). Install O-ring seal (63) to cap assembly (57). Install O-ring seals (54) and (59) to valve body (60).

  14. Install plate (56), pin (62), spring (61) and valve (55) to cap assembly (57) and to valve body (60). Install cap assembly (57) to valve body (60).


    Illustration 14g00480556

  15. Install valve assembly (53) to valve body (3). Valve assembly (53) will need to be adjusted after the hoist control valve is installed. For instructions on adjustment of the valve, refer to Testing and adjusting, RENR3400.


    Illustration 15g00480553

  16. Install O-ring seals (52) to valve body (3).


    Illustration 16g00573212

  17. Install two bolts (50), the washers and manifold (51) to valve body (3).


    Illustration 17g00573211

  18. Install valve stem (49) to valve body (3).


    Illustration 18g00480550

  19. Install two straps (45) to wires (44). Install receptacle assembly (47) to wires (44).

  20. Install two pins (48) to receptacle assembly (47). Install wedge (46) to receptacle assembly (47).


    Illustration 19g00480549

  21. Install O-ring seal (43) to solenoid (41).


    Illustration 20g00480403

  22. Position solenoid (41) to valve body (30). Install four bolts (42) that secure solenoid (41) to valve body (30). Install the six access plugs and the O-ring seals to valve body (30).


    Illustration 21g00480400

  23. Install retainer (33), spring (34), spring (35), spring (36), stop (37), stop (39), control spool (38) and spring (37) to actuator housing (30).


    Illustration 22g00480395

  24. Use Tooling (A) and a hydraulic press and exert downward pressure on retainer (33). Slowly increase the pressure from the hydraulic press and load the spring tension to springs (34), (35) and (36) that are in actuator (30).

  25. Install retainer ring (32) to actuator (30).


    Illustration 23g00480391

  26. Install two O-ring seals (31) to actuator (30). Install the large O-ring seal to the center of actuator (30).


    Illustration 24g00573313

  27. Position actuator (30) to valve body (3). Install two bolts (29) that secure actuator (30) to valve body (3).


    Illustration 25g00480384

  28. Install receptacle assembly (26) to wires (25).

  29. Install two pins (28) to receptacle assembly (26). Install wedge (27) to receptacle assembly (26).


    Illustration 26g00472427

  30. Install two straps (23) to the wires. Install O-ring seal (24) to solenoid (22).


    Illustration 27g00472374

  31. Position solenoid (22) to actuator housing (9). Install four bolts (21) in order to secure solenoid (22) to actuator housing (9).


    Illustration 28g00472371

  32. Install O-ring seals (20) to plugs (19). Install six plugs (19) to valve body (9).


    Illustration 29g00472261

  33. Install retainer (12), spring (13), spring (14), spring (15), spacer (18), control spool (17) and spring (16) to actuator housing (9).


    Illustration 30g00472121

  34. Use Tooling (A) and a hydraulic press and exert downward pressure on retainer (12). Slowly increase the pressure from the hydraulic press and load the spring tension to springs (13), (14) and (15) that are in actuator (9).

  35. Install retainer ring (11) to actuator (9).


    Illustration 31g00472266

  36. Install two O-ring seals (10) to actuator (9). Install the large O-ring seal to the center of actuator (9).


    Illustration 32g00577707

  37. Position actuator (9) to valve body (3). Install two bolts (8) that secure actuator (9) to valve body (3).


    Illustration 33g00472030

  38. Install the O-rings in hydraulic pipes (6) and (7). Position the hydraulic pipes to valve body (3). Tighten retaining nuts (1), (2), (3), and (4) in order to connect hydraulic pipes (6) and (7) to valve body (3).

  39. Install the retainer clips to the hydraulic pipes.

End By:

  1. Install the hoist control valve. Refer to Disassembly and Assembly, "Hoist Control Valve - Install".

Caterpillar Information System:

980G Wheel Loader Braking System Parking Brake - Manual Release
69D and 769D Off-Highway Trucks and 771D Quarry Truck Unit Injector Hydraulic Pump Drive - Remove
Electronic Modular Control Panel II (EMCP II) For MUI Engines Alarm Module or Remote Annunciator - Troubleshoot
515 Wheel Skidder and 525 Wheel Skidder Walk-Around Inspection
950G and 962G Wheel Loaders and IT62G Integrated Toolcarrier Machine Systems Main Control Valve and Mounting Plate (Lift and Auxiliary) - Remove
3304B and 3306B Engines for Caterpillar Built Machines Air Compressor - Remove and Install
950G and 962G Wheel Loaders and IT62G Integrated Toolcarrier Machine Systems Main Control Valve and Mounting Plate (Lift and Auxiliary) - Install
69D and 769D Off-Highway Trucks and 771D Quarry Truck Magnetic Switch (Prelubrication Relay) - Remove and Install
3304B and 3306B Engines for Caterpillar Built Machines Water Directors - Remove and Install
Challenger 35, Challenger 45 and Challenger 55 Agricultural Tractors Implement, Steering and Brake Hydraulic Systems Steering Control
69D and 769D Off-Highway Trucks and 771D Quarry Truck Machine Systems Rear Suspension (Cylinder) - Remove
69D and 769D Off-Highway Trucks and 771D Quarry Truck Machine Systems Rear Suspension (Cylinder) - Install
980G Wheel Loader Braking System Parking Brake Control Cable - Adjust
24H Motor Grader Power Train Hydraulic Filter (Differential)
Repairing the Nonmetallic Fenders, Machine Hoods, and Tank Covers {1273, 7251, 7252} Repairing the Nonmetallic Fenders, Machine Hoods, and Tank Covers {1273, 7251, 7252}
IT14G Integrated Toolcarrier and 914G Wheel Loader Machine Systems Gear Pump (Implement, Steering and Brakes) - Remove
D250E Series II and D300E Series II Articulated Trucks Machine Systems Pressure Reducing Valve - Remove and Install
Installation of 164-4636 Coolant Recovery Tank {1354} Installation of 164-4636 Coolant Recovery Tank {1354}
950G Wheel Loader, 962G Wheel Loader and IT62G Integrated Toolcarrier Hydraulic System Pilot Valve
D250E Series II, D300E Series II, D350E Series II and D400E Series II Articulated Trucks Power Train Electronic Control System CID 0144 FMI 03 Relay (Backup Alarm) Voltage Above Normal - Test
Electronic Modular Control Panel II (EMCP II) For MUI Engines Zero Display of Voltage or Current - Troubleshoot
69D and 769D Off-Highway Trucks and 771D Quarry Truck Machine Systems Slack Adjuster (Rear) - Assemble
69D and 769D Off-Highway Trucks and 771D Quarry Truck Machine Systems Slack Adjuster (Rear) - Disassemble
IT14G Integrated Toolcarrier and 914G Wheel Loader Machine Systems Gear Pump (Implement, Steering and Brakes) - Install
Back to top
The names Caterpillar, John Deere, JD, JCB, Hyundai or any other original equipment manufacturers are registered trademarks of the respective original equipment manufacturers. All names, descriptions, numbers and symbols are used for reference purposes only.
CH-Part.com is in no way associated with any of the manufacturers we have listed. All manufacturer's names and descriptions are for reference only.