Connection Procedure For The Track On CIPI Undercarriage Arrangements Which Are Based On 325 Track Type Excavators
Show/hide table
Required Tools     | |||
---|---|---|---|
Tool     | Part Number     | Part Description     | Qty     |
A     | 1P-3545     | Track Chain Coupler     | 1     |
B     | 1P-3533     | Carrier Bar     | 1     |
C     | 1P-7402     | Coupling Tool Group     | 1     |
D     | 1P-3530     | Seal Installation Tool Group     | 1     |
E     | 5P-6214     | Track Block Assembly     | 1     |
F     | 5P-2380     | Master Pin Press Arrangement     | 1     |
4C-4865 | Hand Hydraulic Pump (or Electric)     | 1     |
- Install Tooling (A) in the track link and on the sprocket, as shown.
Show/hide table
Illustration 1 | g00490683 |
- Start the machine. Move the sprocket forward until the track assembly is pulled up on the sprocket. Move the sprocket forward until the end of the track assembly is past a vertical line through the center of the sprocket. Remove Tooling (A) .
- Install Tool (B) between the first bushing in the track link and the sprocket, as shown.
Show/hide table
Illustration 2 | g00490689 |
- Move the sprocket forward. Use Tooling (B) to guide the track assembly over the track carrier rollers and the front idler.
- Install Tool (C) and pin (1) from Tooling (A) between the track links in the ends of the track assembly, as shown.
Show/hide table
Illustration 3 | g00490692 |
- Move the track assembly forward or backward until the separation in the track assembly is below a horizontal line through the center of the sprocket.
Show/hide table
Illustration 4 | g00921038 |
Typical Example |
Show/hide table
Illustration 5 | g00921039 |
Typical Example |
- Install Tool (E) under the track assembly, as shown. Move the machine to the rear and onto Tool (E) until Tool (C) and pin (1) can be removed. Remove Tool (C) and pin (1) .
- Move the track assembly slightly forward in order to allow installation of washers (2) and spacers (3). Apply 5P-0960 Molybdenum Grease in the bores in the track links. Install washers (2) and spacers (3) in the counterbores, as shown. Use Tool (D) to hold the washers and spacers in place.
- Move the machine backward until the spacers and washers are held in place by the track links. Remove Tool (D) .
- Install the pilot pin from Tooling (F) into the track assembly. Make sure that the pilot pin is centered in the track links.
- Move the track assembly forward until the pilot pin is centered between the two track carrier rollers.
Show/hide table
Illustration 6 | g00921041 |
- Use Tooling (F) and reinstall the master pin in order to hold the track assembly together.
- Use two people to reinstall the two track shoes over the master pin.
- Tighten the tension of the track. Refer to Operation and Maintenance Manual, "Track Adjustment - Adjust" for the correct procedure.
Connection Procedure For The Track On CIPI Undercarriage Arrangements Which Are Based On 325B Track Type Excavators
Show/hide table
Required Tools     | |||
---|---|---|---|
Tool     | Part Number     | Part Description     | Qty     |
A     | 1P-3545     | Track Chain Coupler     | 1     |
B     | 1P-3533     | Carrier Bar     | 1     |
C     | 1P-7402     | Coupling Tool Group     | 1     |
D     | 5P-6214     | Track Block Assembly     | 1     |
E     | 1U-7630     | Impact Socket     | 1     |
- Install Tooling (A) in the track link and on the sprocket, as shown.
Show/hide table
Illustration 7 | g00490683 |
- Start the machine. Move the sprocket forward until the track assembly is pulled up on the sprocket. Move the sprocket forward until the end of the track assembly is past a vertical line through the center of the sprocket. Remove Tooling (A) .
- Install Tool (B) between the first bushing in the track link and the sprocket, as shown.
Show/hide table
Illustration 8 | g00490689 |
- Move the sprocket forward. Use Tooling (B) to guide the track assembly over the carrier rollers and the front idler.
- Install Tool (C) and pin (1) from Tooling (A) between the track links in the ends of the track assembly, as shown.
Show/hide table
Illustration 9 | g00490692 |
- Move the track assembly forward or backward until the separation in the track assembly is below a horizontal line through the center of the sprocket.
Show/hide table
Illustration 10 | g00490695 |
- Apply 5P-0960 Molybdenum Grease on two track bushings (2). Install the bushings in the track links, as shown. The grease will hold the bushings in place.
- Install Tool (D) under the rear of the track assembly, as shown. Move the track assembly backward until the separation in the track assembly closes and the pin bores in both ends of the track assembly are in alignment with each other. The machine might need to be moved back and forth in order to align the pin bores.
- Apply 5P-0960 Molybdenum Grease in the master pin bores in the track assembly and on the master pin. Install the master pin with a hammer. Install the cotter pin in the master pin. Remove Tool (D) from the rear of the track assembly.
- If the track shoe on each side of the master pin was removed, reinstall the track shoes. Use Tool (E) to reinstall the track shoe mounting bolts.
- Tighten the tension of the track. Refer to Operation and Maintenance Manual, "Track Adjustment - Adjust" for the correct procedure.
Connection Procedure For The Track On CIPI Undercarriage Arrangements Which Are Based On 325C Track Type Excavators
Show/hide table
Required Tools     | |||
---|---|---|---|
Tool     | Part Number     | Part Description     | Qty     |
A     | 1P-3545     | Track Chain Coupler     | 1     |
B     | 1P-3533     | Bar     | 1     |
C     | 3S-6224     | Electric Hydraulic Pump Gp (115 Volt) (1)     | 1     |
8T-0820 | Hydraulic Pressure Gauge     | 1     | |
3B-7722 | Pipe Bushing     | 2     | |
1P-2376 | Quick Connect Coupler     | 2     | |
1P-2377 | Dust Plug     | 2     | |
6D-7726 | Hose Assembly     | 2     | |
5P-2379 | Track Press Tool Gp     | 1     | |
8S-7172 | Double Acting Cylinder     | 1     | |
8S-9903 | Track Press Rollover Gp     | 1     | |
D     | 5P-6214     | Track Block Assembly     | 1     |
E     | 1U-7630     | Impact Socket     | 1     |
Show/hide table
( 1 ) | 8S-8033 Electric Hydraulic Pump Gp (230 Volt) is available. |
- Install Tooling (A) in the track link and on the sprocket, as shown.
Show/hide table
Illustration 11 | g00490683 |
- Start the machine. Move the sprocket forward until the track assembly is pulled up on the sprocket. Move the sprocket forward until the end of the track assembly is past a vertical line through the center of the sprocket. Remove Tooling (A) .
- Install Tooling (B) between the first bushing in the track link and the sprocket, as shown.
Show/hide table
Illustration 12 | g00490689 |
- Move the sprocket forward. Use Tooling (B) to guide the track assembly over the carrier rollers and the front idler.
- Use a suitable lifting device to raise the front of the track assembly. Install Tooling (D) in position under the track shoe, as shown.
Show/hide table
Illustration 13 | g00625112 |
Typical example |
- Apply 5P-0960 Molybdenum Grease on two track bushings. Install the bushings in the track links. The grease will hold the bushings in place.
- Apply 5P-0960 Molybdenum Grease in the master pin bores in the track assembly and on the master pin.
- Connect the ends of the track assembly. Make sure that the pin bore in each end of the track assembly is aligned with each other.
- Install the 5F-9447 Pilot Pin in the track assembly. Make sure that the pilot pin is centered in the track links.
- Use Tooling (C) to install the master pin in the track assembly.
Show/hide table
Illustration 14 | g00722410 |
- Install the cotter pin in the master pin. Remove Tooling (D) from the rear of the track assembly.
Note: Refer to Special Instruction, "Track - Assembly" for further information regarding Tooling (C) .
- If the track shoe on each side of the master pin was removed, reinstall the track shoes. Use Tooling (E) to reinstall the track shoe mounting bolts.
- Tighten the tension of the track. Refer to Operation and Maintenance Manual, "Track Adjustment - Adjust" for the correct procedure.
Caterpillar Information System:
325, 325B and 325L Excavators Track - Separate
G3406 Engine Overhaul (Major)
325, 325B and 325L Excavators Track Roller - Install
325, 325B and 325L Excavators Track Roller - Assemble
325, 325B and 325L Excavators Track Roller - Disassemble
325, 325B and 325L Excavators Track Roller - Remove
325, 325B and 325L Excavators Track Carrier Roller - Install
325, 325B and 325L Excavators Track Carrier Roller - Assemble
325, 325B and 325L Excavators Track Carrier Roller - Disassemble
325, 325B and 325L Excavators Track Carrier Roller - Remove
3176C and 3196 Engines For Caterpillar Built Machines Fuel Filter Base - Install
3500B Engines Auxiliary Water Pump - Assemble - Auxiliary Pump (Type 1)
325, 325B and 325L Excavators Front Idler and Recoil Spring - Remove
325, 325B and 325L Excavators Front Idler and Recoil Spring - Install
G3406 Engine Overhaul (Top End)
325, 325B and 325L Excavators Front Idler - Disassemble
325, 325B and 325L Excavators Front Idler - Assemble
325, 325B and 325L Excavators Recoil Spring - Disassemble
3412 Generator Set Engines Fuel Shutoff Solenoid
325, 325B and 325L Excavators Recoil Spring - Assemble
325, 325B and 325L Excavators Track Adjuster - Remove
325, 325B and 325L Excavators Track Adjuster - Disassemble
325, 325B and 325L Excavators Track Adjuster - Assemble
325, 325B and 325L Excavators Track Adjuster - Install