Required Tools | |||
Tool | Part Number | Part Description | Qty |
A(1) | 9U-7489 | Lift Stand | 2 |
447-0910 | Electric Hydraulic Pump Gp (115 V) | 1 | |
447-0911 | Electric Hydraulic Pump Gp (230 V) | 1 | |
4C-5749 | Dolly | 1 | |
A1 | OR | ||
504-9830 | Lift Gp (50/60 Hz)(2) | 2 | |
504-9831 | Lift Gp (50/60 Hz)(3) | 2 | |
B | 194-7586 | Pneumatic Wrench Gp | 1 |
194-7886 | Drive Extension | 1 | |
4C-6723 | Socket | 1 |
(1) | Use Tooling (A) or (A1) based on requirements. |
(2) | Operating Voltage (380V - 500V) |
(3) | Operating Voltage (180V - 300V) |
Start By:
- Install the wheel chocks.
Follow the recommended procedure for removal and installation of tires and or wheel assemblies. Ensure that the machine and tire and or wheel assembly are properly supported at all times. Improper procedures that are used to remove and install tires and or wheel assemblies can result in personal injury or death. |
Servicing and changing tires and rims can be dangerous. This work must be done only by trained personnel with correct tools and procedures. If correct procedures are not followed while servicing tires and rims, the assemblies can burst with explosive force and cause serious physical injury or death. Follow carefully the specification information provided by your tire servicing person or dealer. |
NOTICE |
---|
Keep all parts clean from contaminants. Contaminants may cause rapid wear and shortened component life. |
- Use Tooling (A) to raise the front chassis until the weight of the truck is off the front tires and rims.
Show/hide table
Illustration 2 g06384714 Typical example
For Tooling (A1) - Use Tooling (A1) to raise the front chassis until the weight of the truck is off the front tires and rims. Refer to Tool Operating Manual, NEHS1334, "Lift Stands (150 Ton)" for more information on Tooling (A1).
Show/hide table
Illustration 3 g00500943 Show/hide tableIllustration 4 g00713802 - Use Tooling (B) to remove nuts (2). Do not remove three flange nuts (3).
- Use a suitable tire handler to support tire and rim (1). The weight of tire and rim (1) is approximately
3007 kg (6630 lb) . Use Tooling (B) to remove three flange nuts (3). - Remove tire and rim (1).
Illustration 1 | g00500940 |
For Tooling (A) |
Required Tools | |||
Tool | Part Number | Part Description | Qty |
A(1) | 9U-7489 | Lift Stand | 2 |
447-0910 | Electric Hydraulic Pump Gp (115 V) | 1 | |
447-0911 | Electric Hydraulic Pump Gp (230 V) | 1 | |
4C-5749 | Dolly | 1 | |
A1 | OR | ||
504-9830 | Lift Gp (50/60 Hz)(2) | 2 | |
504-9831 | Lift Gp (50/60 Hz)(3) | 2 | |
B | 194-7586 | Pneumatic Wrench Gp | 1 |
194-7886 | Drive Extension | 1 | |
4C-6723 | Socket | 1 |
(1) | Use Tooling (A) or (A1) based on requirements. |
(2) | Operating Voltage (380V - 500V) |
(3) | Operating Voltage (180V - 300V) |
NOTICE |
---|
Keep all parts clean from contaminants. Contaminants may cause rapid wear and shortened component life. |
- Use a suitable tire handler to position tire and rim (1). The weight of tire and rim (1) is approximately
3007 kg (6630 lb) .Note: Ensure that the valve stem is facing outward.
- Use Tooling (B) to install three flange nuts (3). Tighten flange nuts (3) to a torque of
1150 ± 150 N·m (849 ± 111 lb ft) . - Use Tooling (B) to install nuts (2). Tighten nuts (2) to a torque of
1150 ± 150 N·m (849 ± 111 lb ft) .Show/hide tableIllustration 7 g00500940 For Tooling (A) - Lower Tooling (A) until the weight of the machine is on the front tires and rims. Remove Tooling (A).
Show/hide table
Illustration 8 g06384714 Typical example
For Tooling (A1) - Lower Tooling (A1) until the weight of the machine is on the front tires and rims. Remove Tooling (A1). Refer to Tool Operating Manual, NEHS1334, "Lift Stands (150 Ton)" for more information on Tooling (A1).
Illustration 5 | g00500943 |
Illustration 6 | g00713802 |
End By:
- Remove the wheel chocks.