UPSB220 Uninterruptible Power Supply Caterpillar


Cabinet - Check

Usage:

UPSB 220 JFA

------ DANGER! ------

Failure to connect the unit to a suitable grounding electrode creates an electrical shock hazard. An electrical shock will result in serious personal injury or death.


High voltage levels are present within the UPS. The UPS should be opened only by service personnel that are qualified. The UPS must have a proper ground connection to earth.

------ DANGER! ------

High voltage may be present. Work on this equipment must be performed by authorized trained personnel. Failure to disconnect the power source before performing maintenance or removing modules exposes personnel to electrical potential. Bodily contact with electrical potential will cause serious personal injury or death.


After power is removed, wait for 5 minutes before the UPS is opened. This action allows the capacitors to discharge. Ensure that the capacitors are at a zero energy level before performing work.

Personal protective equipment (PPE) suitable to the work being performed must be worn when performing maintenance on the UPS.

------ DANGER! ------

High voltage is present. Work on this equipment must be performed by authorized trained personnel. Personnel must be wearing Personal Protective Equipment that meets regulatory requirements to protect the body for the work that is being performed. Failure to use appropriate PPE to protect the body will result in serious personal injury or death.


Inspecting the Interior of the UPS

------ WARNING! ------

Performing maintenance inspections with power supplied to the UPS may result in serious personal injury or death. When using an external maintenance bypass, the UPS can be fully de-energized. When using an internal maintenance bypass, the UPS is not fully de-energized. Refer to the Building System Schematic to ensure that all necessary precautions have been taken before performing any maintenance procedure. Use lock out and tag out procedures as required.

----------------------

When possible, remove the panels and inspect the following:

  • Ensure that you are familiar with the input terminations, output terminations, buses, and other components of the UPS that may still have voltage present.

  • Verify that the power cables and other wire cable routings do not contact any sharp metal edges or unprotected metal edges.

  • Verify that the power connections and the connections for the control wires on the following are correct and tight: Verify the capacitor banks, bus bars, circuit breakers, switches, grounding straps, transformers, terminal strips, ribbon cables, and PCA.

  • Verify that the DC power cable connections to the bus bars, circuit breakers, switches, and terminal strips are correct and tight.

  • Verify that the power cable connections and the connections for the control wire for any external maintenance bypass cabinet are correct and tight.

  • Verify that the power cable connections and the connections for the control wire for any auxiliary cabinets and RASPs are correct and tight.

  • Verify that there are no visible signs of interior damage. Check all installed components and assemblies, mounting points, and the structural integrity of the cabinet.

  • Verify that the wiring is tight.

  • Verify that the AC capacitor assemblies and the DC capacitor assemblies have the proper phase and proper connections.

  • Verify that the interior of the UPS is free of foreign items. Items may include extra wire, tools, loose hardware, and any other objects that do not belong in the UPS.

Inspecting the Battery Cabinet

When possible, remove all panels from the battery cabinet. Record the battery manufacturer, the model number for the battery, the number of batteries, and the battery date code.

Inspect the following:

  • Ensure that you are familiar with the power terminations, buses, and other components of the battery cabinet. Voltage could be present under certain conditions.

  • Verify that the cable routing for DC power, wire cable routing, and wire runs do not contact sharp metal edges or unprotected metal edges.

  • Verify that the following are correct and tight. Verity the DC power cable, interconnections for the battery, connections for control wire to the bus bars, circuit breakers, terminal strips, and all other connectors.

  • Verify that grounding straps have been installed between the cabinets

  • Verify that the power cable connections are correct and tight.

  • Verify the connections for the control wire to any external disconnects for the DC power are correct and tight.

  • Verify that no DC ground faults are present.

  • Verify that the battery cabinet temperature sensor (AITZ sensor) is installed.

  • Verify that there are no visible signs of interior damage. Check all installed components and assemblies, mounting points, and the structural integrity of the cabinet.

  • Verify that the interior of the battery cabinet is free of foreign items. Items include extra wire, tools, loose hardware, and any other objects that do not belong in the UPS.

  • Verify that grounding straps have been installed between the UPS cabinets.

Verifying the Battery

  1. Verify the DC polarity of the battery string at the disconnects. Refer to Table 1 for disconnect configurations.

    Table 1
    DC Disconnect     Polarity    
    Two-pole device or only using two poles of a three-pole device     Polarity of the battery string matches with the polarity of the cables from the Rectifier/Charger    
    Three-pole device containing a loop or jumper bridging between one of the Line & Load poles     Polarity of the battery string matches with the polarity of the cables from the Rectifier/Charger    
    Three-pole device splitting the battery string into two halves     Polarity for the summation of the two half-strings making up the battery matches with the polarity of the cables from the Rectifier/Charge    

  1. Arrange to have any polarity discrepancies resolved.

  1. Verify that the voltage is at the rated DC voltage.

Inspecting the Auxiliary Cabinet and Accessories

When possible, remove all panels from the auxiliary cabinets. Record the serial numbers and model numbers for the cabinets. Inspect the following:

  • Ensure that you are familiar with the input and output terminations, bus work, and other components of the UPS that may still have voltage present.

  • Verify that there are no visible signs of interior damage. Check all of the installed components and assemblies, mounting points, and the structural integrity of the cabinet.

  • Verify that the routing for the power cable, wire cables, and the wire runs do not contact sharp metal edges or unprotected metal edges.

  • Verify that the connections for the power cable and the connections for the control wire of the following are correct and tight. Verify the bus bars, circuit breakers, switches, transformers, terminal strips, ribbon cables, and PCAs.

  • Verify that grounding straps have been installed between the cabinets

  • Verify that the connections for the control wire to any external maintenance bypass cabinets are correct and tight.

  • Verify that the connections for the control wire to any auxiliary cabinets and RSAP are correct and tight.

  • Verify that the interior of the auxiliary cabinet is free of foreign items. Items may include extra wire, tools, loose hardware, and any other objects that do not belong in the cabinet.

Inspection for Field Upgrades

  • Verify that the system has been updated per all service letters and service programs.

  • Communicate any upgrade recommendations to the customer.

Note: To complete basic preventive maintenance, refer to Testing and Adjusting, "Unit Final Check".

Caterpillar Information System:

UPSB220 Uninterruptible Power Supply Configuration - Check
UPSB220 Uninterruptible Power Supply System Shutdown
UPSB220 Uninterruptible Power Supply Metering - Check
UPSB220 Uninterruptible Power Supply Unit Initial Check
C9 Industrial Engines Belts - Inspect/Adjust/Replace
UPSB220 Uninterruptible Power Supply Basic Preventive Maintenance
3406C Industrial Engine Air Compressor - Check
C13, C15, and C18 Tier 4 Final Engines Cylinder Block
3500 Engines Camshaft
797F and 797F XQ Off-Highway Truck Braking System Control Valve (Brake) - If Equipped
Procedure for the Installation of the 372-1187 Nitrogen Oxide Sensor Gp and the 379-0138 Sensor Kit (NITROGEN OXIDE){191N} Procedure for the Installation of the 372-1187 Nitrogen Oxide Sensor Gp and the 379-0138 Sensor Kit (NITROGEN OXIDE){191N}
C15 Petroleum Engines Turbocharger
UPSB220 Uninterruptible Power Supply Advanced Preventive Maintenance
UPSB220 Uninterruptible Power Supply System Startup
UPSB220 Uninterruptible Power Supply Input Power - Test
UPSB220 Uninterruptible Power Supply Power Supply - Check
UPSB220 Uninterruptible Power Supply On-Battery - Check
UPSB220 Uninterruptible Power Supply Manual Transfer - Check
UPSB220 Uninterruptible Power Supply Communication - Check
UPSB220 Uninterruptible Power Supply Unit Final Check
UPSB220 Uninterruptible Power Supply Configuration - Adjust
C15 and C18 Industrial Engines Turbocharger
C15 and C18 Industrial Engines Turbocharger
797F and 797F XQ Off-Highway Truck Hydraulic Fan System Piston Motor (Hydraulic Fan) - Extra Retarding
Back to top
The names Caterpillar, John Deere, JD, JCB, Hyundai or any other original equipment manufacturers are registered trademarks of the respective original equipment manufacturers. All names, descriptions, numbers and symbols are used for reference purposes only.
CH-Part.com is in no way associated with any of the manufacturers we have listed. All manufacturer's names and descriptions are for reference only.