Fuel Tank - Install

Usage:

973D LCP

Installation Procedure

Table 1
Required Tools    
Tool     Part Number     Part Description     Qty    
A     138-7575     Link Brackets     2    

Note: Cleanliness is an important factor. Before assembly, thoroughly clean all parts in cleaning fluid. Allow the parts to air dry. Do not use wiping cloths or rags to dry parts. Lint may be deposited on the parts which may cause trouble. Inspect all parts. If any parts are worn or damaged, use new parts for replacement. Dirt and other contaminants can damage the precision component. Perform assembly procedures on a clean work surface. Keep components covered and protected at all times.

Note: Check the O-ring seals, the gaskets, and the seals for wear or for damage. Replace the components, if necessary.


NOTICE

Care must be taken to ensure that fluids are contained during performance of inspection, maintenance, testing, adjusting and repair of the product. Be prepared to collect the fluid with suitable containers before opening any compartment or disassembling any component containing fluids.

Refer to Special Publication, NENG2500, "Caterpillar Dealer Service Tool Catalog" for tools and supplies suitable to collect and contain fluids on Caterpillar products.

Dispose of all fluids according to local regulations and mandates.


------ WARNING! ------

Fuel leaked or spilled onto hot surfaces or electrical components can cause a fire. To help prevent possible injury, turn the start switch off when changing fuel filters or water separator elements. Clean up fuel spills immediately.

----------------------



    Illustration 1g01484913



    Illustration 2g01484895

  1. Attach Tooling (A) and a suitable lifting device to fuel tank (27). The weight of fuel tank (27) is approximately 50 kg (110 lb). Position fuel tank (27) into the machine.



    Illustration 3g01484893

  1. Connect harness assembly (22). Position harness assembly (22) and install new cable straps (23). Install tube assembly (26). Install hose assemblies (21) .

    Note: No clearance is allowed between the fuel tank and the brackets.

  1. Install brackets (24) and (25) .



    Illustration 4g01484415

    Note: No clearance is allowed between the fuel tank and the brackets.

  1. Install cap assembly (17). Install bracket (18). Position harness assembly (7) and install new cable straps (20). Install clips (19) .



    Illustration 5g01484413

  1. Attach a suitable lifting device to support assembly (13). The weight of support assembly (13) is approximately 39 kg (85 lb). Install support assembly (13). Install new cable straps in order to secure harness assembly (7) to support assembly (13) .

    Note: No clearance is allowed between the fuel tank and the brackets.

  1. Install bracket (14). Connect hose assembly (16) and bracket (15) .



    Illustration 6g01484414

  1. Connect clips (11) and hose assembly (12).



    Illustration 7g01484139

  1. Position plate assembly (10) and install bolts (9). Repeat for the opposite side.



    Illustration 8g01484138

  1. Use two people in order to position plate assembly (8). The weight of plate assembly (8) is approximately 27 kg (60 lb). Install plate assembly (8). Install new cable straps in order to secure harness assembly (7) to plate assembly (8) .



    Illustration 9g01484137

    Note: No clearance is allowed between the fuel tank and the brackets.

  1. Position bracket (6) and install bolts (5). Repeat for the opposite side.



    Illustration 10g01483995

  1. Position manifold assembly (4) and install bolts (3). Repeat for the opposite side.



    Illustration 11g01483994

  1. Install hose assemblies (1). Install clamps (2). Repeat for the opposite side.

  1. Turn the fuel supply valve to the ON position. Fill the fuel tank with fuel. Purge the air from the fuel system.

End By:

  1. Install the batteries. Refer to Disassembly and Assembly, "Battery - Remove and Install".
  2. Install the main control valve. Refer to Disassembly and Assembly, "Main Control Valve - Install".
  3. Install the implement pump. Refer to Disassembly and Assembly, "Piston Pump (Implement) - Install".
  4. Install the hydrostatic pumps. Refer to Disassembly and Assembly, "Piston Pump (Hydrostatic) - Install".
  5. Install the hydraulic tank. Refer to Disassembly and Assembly, "Hydraulic Tank - Install".

Caterpillar Information System:

973D Track-Type Loader Machine Systems Fuel Tank - Remove
993K Wheel Loader Power Train Relief Valve (Torque Converter Outlet) - Remove
D6N Track-Type Tractor Fuel System Primary Filter/Water Separator - Drain
D6N Track-Type Tractor Fuel System Primary Filter (Water Separator) - Replace
854K Wheel Dozer Hydraulic System Torque Converter Stall and Implement Pump Double Stall - Test
854K Wheel Dozer Machine Systems Push Arms and Blade - Install
D6N Track-Type Tractor Fuel System Third Filter - Replace
C4.4 and C6.6 Engines for Caterpillar Built Machines Ignition Keyswitch Circuit and Battery Supply Circuit - Test
993K Wheel Loader Power Train Transmission Oil Pump - Install
Proper Assembly Sequences for Installing Air Inlet Heater Relay (12VDC Relay: 175-2301 Magnetic Switch, 24VDC Relay: 148-0757 Magnetic Switch){1090, 1408} Proper Assembly Sequences for Installing Air Inlet Heater Relay (12VDC Relay: 175-2301 Magnetic Switch, 24VDC Relay: 148-0757 Magnetic Switch){1090, 1408}
854K Wheel Dozer Hydraulic System Location of Electrical Components
992K Wheel Loader and 854K Wheel Dozer Power Train Electrical Output Components
993K Wheel Loader Power Train Relief Valve (Torque Converter Outlet) - Install
D6N Track-Type Tractor Fuel System Secondary Filter - Replace
D5R Track-Type Tractor Ripper Tips
854K Wheel Dozer Hydraulic System Piston Pump Cutoff Pressure (Hydraulic Fan) - Test and Adjust
854K Wheel Dozer Hydraulic System Piston Pump Margin Pressure (Hydraulic Fan) - Test and Adjust
Procedure to Install 315-6307, 315-6310 Coupler Lines Groups on Certain Wheel Loaders{5057, 5147, 5734, 6129, 7332} Procedure to Install 315-6307, 315-6310 Coupler Lines Groups on Certain Wheel Loaders{5057, 5147, 5734, 6129, 7332}
3500 Petroleum Engines and Petroleum Generator Sets Configuration Parameters
993K Wheel Loader Power Train Modulating Valve (Torque Converter Lockup Clutch) - Remove
854K Wheel Dozer Machine Systems Lift Cylinder Mounting - Remove and Install
993K Wheel Loader Power Train Modulating Valve (Torque Converter Lockup Clutch) - Install
993K Wheel Loader Power Train Modulating Valve (Torque Converter Impeller Clutch) - Remove
C4.4 Engines For Caterpillar Built Machines Engine Temperature Sensor Open or Short Circuit - Test
Back to top
The names Caterpillar, John Deere, JD, JCB, Hyundai or any other original equipment manufacturers are registered trademarks of the respective original equipment manufacturers. All names, descriptions, numbers and symbols are used for reference purposes only.
CH-Part.com is in no way associated with any of the manufacturers we have listed. All manufacturer's names and descriptions are for reference only.