3408E Engine Supplement for 769D Off-Highway Trucks and 771D Off-Highway Quarry Trucks Caterpillar


Radiator - Install

Usage:

769D BBB

Installation Procedure

Table 1
Required Tools    
Tool     Part Number     Part Description     Qty    
A     9U-7536     Lift Stand     1    
A     4C-5809     Electric Hydraulic Pump     1    


NOTICE

Care must be taken to ensure that fluids are contained during performance of inspection, maintenance, testing, adjusting and repair of the product. Be prepared to collect the fluid with suitable containers before opening any compartment or disassembling any component containing fluids.

Refer to Special Publication, NENG2500, "Caterpillar Tools and Shop Products Guide" for tools and supplies suitable to collect and contain fluids on Caterpillar products.

Dispose of all fluids according to local regulations and mandates.


  1. Verify that all of the components of the radiator are clean and free of foreign material prior to installation.

  1. Inspect all components for wear. Replace the components that are worn or damaged. Use new gaskets and seals when you install the radiator.



    Illustration 1g00830875

  1. Attach a suitable lifting device to radiator (28). Position radiator (28) on the machine. The radiator weighs approximately 480 kg (1058 lb).



    Illustration 2g00830879

  1. Install two bolts (29) and the washers at each side of radiator (28) .



    Illustration 3g00830793



    Illustration 4g00830803

  1. Install two bolts (26) that secure clips and heater hoses (27) to the bottom of the radiator.

  1. Install tie straps (24) that secure wiring harness (25) to the left side of the radiator.

  1. Install four upper bolts (23) and the spacers that secure fan guard (23) around the fan spider.

  1. Install four lower bolts (21) that secure fan guard (23) around the fan spider.



    Illustration 5g00833172

  1. Install two bolts (19) that hold step assembly (20) to the top left side of the radiator.



    Illustration 6g00830740

  1. Install bolt (18) that secures the clip and the hose to the left side of the radiator. Install bolt (16) that secures refrigerant accumulator (17) to the left side of the radiator.



    Illustration 7g00830766

  1. Install bolt (14) that holds refrigerant dryer (15) to the left side of the radiator.



    Illustration 8g00830743

  1. Route wiring harness (12) along the top of the radiator and along the right side platform. Secure the harness with tie straps (13) .



    Illustration 9g00830954

  1. Connect wiring harness (12) at the headlamps on the right side of the machine.



    Illustration 10g00833151

  1. Use three bolts (10) to install baffle assembly (11) at the bottom of the radiator.



    Illustration 11g00833141

  1. Install two bolts, and four clips (8) to secure two hoses (9) at the top of the radiator.



    Illustration 12g00830720

  1. Use a new gasket, four bolts (6), and the washers to connect elbow (7) at the lower left side of the radiator.



    Illustration 13g00830729

  1. Use a new gasket, four bolts (4), and the washers to connect elbow (5) at the lower right side of the radiator.



    Illustration 14g00585446

  1. Make sure that Tooling (A) is in position under the frame, as shown.

    Note: Tooling (A) will ease installation of the tube assembly.




    Illustration 15g00830716

  1. Attach a suitable lifting device (not shown) to tube assembly (1). Position tube assembly (1) on the machine. Install shims (3) and bolts (2) at each end of the tube assembly. Tighten bolts (2) to a torque of 120 ± 20 N·m (89 ± 145 lb ft). The tube assembly weighs approximately 26 kg (57 lb).

  1. Remove Tooling (A) .

End By:

  1. Install the ether starting aid. Refer to Disassembly and Assembly, "Ether Starting Aid - Remove and Install".
  2. Install the crankcase guard. Refer to Disassembly and Assembly, "Crankcase Guard - Remove and Install".
  3. Install the refrigerant condenser. Refer to Disassembly and Assembly, "Refrigerant Condensor - Remove and Install".
  4. Install the aftercooler. Refer to Disassembly and Assembly, "Aftercooler - Install".
  5. Fill the radiator with coolant. Refer to Operation and Maintenance Manual, "Cooling System Coolant (ELC) - Change".

Caterpillar Information System:

950G Series II Wheel Loader, 962G Series II Wheel Loader and IT62G Series II Integrated Toolcarrier Power Train Temperature Switch (Axle Oil)
CP-563C and CS-563C Vibratory Compactors Final Drive Planetary (Drum) Oil - Change
CP-563C and CS-563C Vibratory Compactors Final Drive Planetary (Axle) Oil Sample - Obtain
CP-563C and CS-563C Vibratory Compactors Final Drive Planetary (Axle) Oil Level - Check
3408E Engine Supplement for 769D Off-Highway Trucks and 771D Off-Highway Quarry Trucks Fan Drive - Install
914G Compact Wheel Loader and IT14G Integrated Toolcarrier Transmission Electronic Control System MID 079 - CID 0418 - FMI 03
M316C, M318C and M322C Excavators and M318C and M322C Material Handlers Transmission Oil Level - Check
CP-563C and CS-563C Vibratory Compactors Final Drive Planetary (Axle) Oil - Change
TL5 Series Field Cultivator Troubleshooting
2001/10/15 A New Owners Manual is Now Available {1000, 7000}
CP-563C and CS-563C Vibratory Compactors Cutting Edges (Leveling Blade) - Inspect/Replace
416D, 420D, 424D, 428D, 430D, 432D, 438D and 442D Backhoe Loaders Hydraulic and Steering System Bucket Cylinder (Extendable Stick)
CP-563C and CS-563C Vibratory Compactors Final Drive Planetary (Drum) Oil - Check
3408E and 3412E Engines for Caterpillar Built Machines Balancer Group - Remove
3408E and 3412E Engines for Caterpillar Built Machines Balancer Group - Install
TH350B, TH355B, TH360B and TH460B Telehandlers Battery Disconnect Switch - If Equipped
740 and 740 EJECTOR Articulated Trucks Power Train Output Transfer Gears - Assemble
TL5 Series Field Cultivator Transporting the Implement
2001/11/26 New Control Software for the Chassis ECM is Used {7620}
914G Compact Wheel Loader and IT14G Integrated Toolcarrier Transmission Electronic Control System MID 079 - CID 0418 - FMI 05
3408E Engine Supplement for 769D Off-Highway Trucks and 771D Off-Highway Quarry Trucks Engine and Torque Converter - Install
950G Series II Wheel Loader and 962G Series II Wheel Loader Electrohydraulic System Ride Control Accumulator - Test and Charge
A Process is Available to Replace the Propel Lever Group{3209, 5462} A Process is Available to Replace the Propel Lever Group{3209, 5462}
TL5 Series Field Cultivator Bearings - Lubricate