Site Inspection and Material Inventory

Usage:

ES18H2.25 ZA5

Site Inspection

The following concerns must be addressed and completed before the ESS is installed on the pad or any cables connected to the system. The concerns serve as a check list for installation requirements performed by the civil and electrical contractors.

  1. Verify that the intended load is smaller than the ESS kW capacity.

  2. Verify that the cable entry position on pad is correct.

  3. Verify that all doors have adequate clearance for the doors to be opened.

  4. Verify that the grounding cable has been installed. The grounding cable goes from the installed ESS to the appropriate site (earth) ground.

  5. Verify that the positive and negative battery cables from the ESS to the DC power source (rectifier) are installed correctly.

  6. If a DG is present, verify the following:

    1. That the installation of the DG start/stop signal wire from the ESS to the DG controller is correct.

    2. Verify installation of the DG run/fail signal wire from the ESS to the DG controller is correct.

  7. Verify that all cables have sufficient length for routing to the appropriate location in the unit.

Shipment Inspection and Material Inventory

The unit will be shipped from the factory with all the necessary components to assemble the equipment. Inspect all packages for damage prior to installation. Do not complete installation with damaged components. Several configurations of the ESS are available for different-sized kW loads. Refer to Table 1 for a list of models to determine the applicable inventory required.

Table 1
Installation Components Shipped from Factory 
Description  Quantity per Energy Module  Quantity per Power Module  Quantity with Expansion Cabinet  Quantity with Power Module Electronics Panel 
Energy Cell Assembly  18 
Power Cell 32 V 1100 Whr 
Cell Inter-connect (Cells)  16 
M8 Washer (enclosure)  28  14 
M4 Belleville washer (cells)  36 
M4 x 12 mm Screw (cells)  36 
M8 x 16 mm Bolt (enclosure)  14  14 
M8 Nut (enclosure)  14 

Installer Provided Material Inventory

The installation contractor is expected to provide the materials found in Table 2.

Table 2
Description  Quantity 
Compression lug, aluminum, for positive and negative connections to rectifier and grounding cable terminations  As required 
DC Breaker to function as disconnect and provide circuit protection for the ESS. The breaker is mounted inside rectifier cabinet.  As required 
Wire bundle, 22 AWG, 2 conductor, copper, PVC insulation, 300 VAC, for DG control cables (DG sites only)  As required 
Cable, aluminum, single conductor, 1/0 AWG, 600 V, for cabinet grounding cable  As required 
12 mm anchor bolt and hardware 

Aluminum conductor is specified for the positive and negative cables connecting the ESS to the rectifier cabinet. Equivalent copper conductor may be utilized if necessary. There is an increased risk of theft of the copper wire. Therefore, the recommendation is to use the aluminum conductor and the supporting materials specified in Table 2.