Removal Procedure

Start By:

  1. Remove the exhaust elbow. Refer to Disassembly and Assembly, "Exhaust Elbow - Remove and Install" for the correct procedure.


    Illustration 1g02282333

  1. Slide locking tab (8) into the unlocked position. Disconnect harness assembly (7). Slide the connection for harness assembly (7) from bracket (9).

  2. Loosen V-band clamp (2). Support the exhaust back pressure valve (1). Reposition the V-band clamp in order to allow removal of the back pressure valve.

    Note: If the V-band clamp remains tight on the flanges, apply releasing fluid on the V-band clamp in order to assist removal. Lightly tap the bolts on the V-band clamp with a soft faced hammer in order to assist removal. Do not use a prybar to remove the V-band clamp.

  3. Make temporary marks on the exhaust back pressure valve (1) and exhaust back pressure valve adaptor (3) to aid realignment. Remove the exhaust back pressure valve.

  4. If necessary, follow Step 4.a through Step 4.d in order to remove adaptor (3).

    1. Make temporary marks on the back pressure valve adaptor and the turbocharger to ensure the correct orientation during installation.

    2. Remove nuts (6) and back pressure valve adaptor (3).

    3. Remove gasket (4) (not shown).

    4. If necessary, remove studs (5) from the turbocharger.

Installation Procedure

Table 1
Required Tools 
Tool  Part Number  Part Description  Qty 
4C-5597  Anti-Seize Compound 

  1. Ensure that all components are clean and free from wear and damage. If necessary, replace any components that are worn or damaged.


    Illustration 2g02282333


    Illustration 3g02424896

  2. If necessary, follow Step 2.a through Step 2.e in order to install back pressure valve adaptor (3).

    1. If necessary, install studs (5) to the turbocharger.

    2. Clean the gasket surface of the turbocharger and back pressure valve adaptor (3).

    3. Position gasket (4) (not shown) onto studs (5).

    4. Install back pressure valve adaptor (3) to the turbocharger. Using the alignment marks made during the disassembly procedure, ensure that the back pressure valve adaptor is correctly orientated.

    5. Install nuts (6) to the studs. Tighten the nuts to a torque of 44 N·m (33 lb ft).

  3. Use Tooling (A) to lubricate the Allen headed bolt for V-band clamp (2). Position the V-band clamp onto adaptor (3).

  4. Align the temporary marks and install exhaust back pressure valve (1) to back pressure valve adaptor (3). If installed, ensure that the alignment dowel (10) is engaged in the alignment hole in Position (A) before the V-band clamp is installed.

  5. Position V-band clamp (2) onto exhaust back pressure valve (1) and back pressure valve adaptor (3).

  6. Tighten the V-band clamp (2) to a torque of 12 N·m (106 lb in)

    Note: Ensue that the bolt for the V-band clamp does not contact any other components.

  7. Slide the connection for harness assembly (7) onto bracket (9). Connect harness assembly (7). Slide locking tab (8) into the locked position.

End By:

  1. Install the exhaust elbow. Refer to Disassembly and Assembly, "Exhaust Elbow - Remove and Install" for the correct procedure.

Caterpillar Information System:

C1.5 and C2.2 Industrial Engines Engine Electronics
2010/12/06 A New Throttle Actuator Is Used for Some G3500 and G3500B Engines {1265, 1716}
3306B Generator Set Product Lifting
C1.5 and C2.2 Industrial Engines Model View Illustrations - Engines and Aftertreatment
C1.5 and C2.2 Industrial Engines Safety Messages
349E, 349F and 352F Excavators and 349E MHPU Mobile Hydraulic Power Unit Tool Control System Solenoid Valve (Proportional Reducing) - Calibrate - Pilot Pressure Limit
C27 and C32 Engines for Caterpillar Built Machines Pressure Sensor (Cooled Exhaust Gas) - Remove and Install - NRS Differential Pressure
C27 and C32 Engines for Caterpillar Built Machines Pressure Sensor (Cooled Exhaust Gas) - Remove and Install - NRS Intake
C7.1 Industrial Engine Relief Valve (Fuel) - Remove and Install
C27 and C32 Engines for Caterpillar Built Machines Temperature Sensor (Cooled Exhaust Gas) - Remove and Install
C27 and C32 Engines for Caterpillar Built Machines ECM Does Not Communicate with Other Modules
349E, 349F and 352F Excavators and 349E MHPU Mobile Hydraulic Power Unit Tool Control System Solenoid Valve (Proportional Reducing) - Calibrate - Attachment Valves
C9.3 Tier 4 Final Engines Turbocharger
D6T Track-Type Tractor Engine Air Precleaner - Clean
12M Motor Grader Engine Starting
C1.5 and C2.2 Industrial Engines Emissions Certification Film
12M, 140M and 160M Motor Graders Hydraulic and Steering System Solenoid Valve (Blade Cushion)
C1.5 and C2.2 Industrial Engines Sensors and Electrical Components - Engine and Aftertreatment
G3512E and G3520E Generator Set Engines Electronic Control Module (ECM)
3516C Locomotive Engines Control Cabinet - Disassemble
3516C Locomotive Engines Control Cabinet - Assemble
C6.6 Industrial Engine Flexible Exhaust Pipe - Remove and Install
C6.6 Industrial Engine Exhaust Elbow - Remove and Install
C1.5 and C2.2 Industrial Engines Refill Capacities and Recommendations
Back to top
The names Caterpillar, John Deere, JD, JCB, Hyundai or any other original equipment manufacturers are registered trademarks of the respective original equipment manufacturers. All names, descriptions, numbers and symbols are used for reference purposes only.
CH-Part.com is in no way associated with any of the manufacturers we have listed. All manufacturer's names and descriptions are for reference only.