Screed Plates - Check/Replace and Adjust - Main Screed
Show/hide table
Diesel engine exhaust contains products of combustion which may cause personal injury. Always start and operate the engine in a well ventilated area, and, if in an enclosed area, vent the exhaust to the outside. |
Show/hide table
In order to prevent personal injury from accidental screed movement, lock the screed in the RAISED position by using the service lock lever to extend the lock pins after the screed is fully raised. |
Show/hide table
Machine Test Parameters | ||
---|---|---|
Date | Product or Component SN | |
Measurement Location | Measurement | Actual |
The distance between drop arm face (5) and slope box face (6). | |
This procedure outlines the methods used to level the main screed plate. The main screed should be adjusted after replacement of the screed plate or as required during normal operation.
Show/hide table
Required Tools | ||||
---|---|---|---|---|
Tool | Item | Qty | Part No | Description |
A | 1 | - | Stringline | |
B | 3 | - | Equal Sized Spacers | |
C | 1 | - | Tape Measure |
- Drive the machine to a smooth, horizontal surface. Refer to the tractor Operation and Maintenance manual for the proper operating procedure.
Show/hide table
Illustration 1 g03670060 - Raise the screed and allow the tow arms to rest on two screed service locks (1).
Show/hide table
Illustration 2 g03670072 - Lower the right and left tow points (2) to the lowest point.
Show/hide table
Illustration 3 g03670077 - Use Tool (C) to measure the distance between barrel (3) of the tow point cylinder and the end of cylinder rod (4). If the distance is not equal, adjust the tow points as required until both sides are equal.
- Use Tool (C) to measure the distance between drop arm face (5) and slope box face (6). The distance should be
480 mm (19 inch) on both sides of the screed.Show/hide tableIllustration 5 g03703625 - If the distance is incorrect loosen locknut (7), if necessary.
Show/hide table
Illustration 6 g03670014 Show/hide tableIllustration 7 g03714827 - Use thickness screw adjustment handle (8) to set the face to face measurement to
480 mm (19 inch) .Note: Screeds equipped with the tamper option use knob (9) to set the face to face measurement.
- Tighten locknut (7).
- Verify that there is zero crown in the main screed.
- Place Tool (A) across the width of main screed plate (10) approximately
25.4 mm (1 inch) behind the leading edge. - Place two of Tool (B) between Tool (A) and the screed plate. Locate each Tool (B) approximately
25.4 mm (1 inch) from the ends of main screed plate (10).Show/hide tableIllustration 9 g03669446 - Use a third Tool (B) as a gauge in order to check the gap between the screed plate and Tool (A). This check should be taken at the center of main screed plate (10).
Show/hide tableIllustration 8 g03645001 Show/hide tableIllustration 10 g03645091 - Place Tool (A) across the width of main screed plate (10) approximately
- Use crown increase switch (12) and crown decrease switch (11) to adjust the crown. The space between Tool (A) and Tool (B) should be equal at all three locations.
Show/hide table
Illustration 11 g03645030 - Place Tool (A) across the width of main screed (10) approximately
25.4 mm (1 inch) in front of the trailing edge. - Place two of Tool (B) between Tool (A) and the screed plate. Locate each Tool (B) below the first adjuster at each end of main screed plate (10).
Show/hide table
Illustration 12 g03720805 - Use a third Tool (B) as a gauge in order to check the gap between the main screed plate and Tool (A). This check should be taken below each adjuster. Check from the outer edges of the main screed plate to the center of main screed plate (10).
- If the trailing edge of the screed plate is flat and straight, go to Step 11. If the trailing edge of the main screed plate is not flat and straight, go to "Adjustment Procedure", "Trailing Edge Adjustment".
- Remove tooling.
Show/hide table
Illustration 4 | g03669496 |
- Use extender proportional extender switch (13) to extend the right and left extenders.
Show/hide table
Illustration 14 g03713713 - Remove two bolts (15) and washers. Remove plate (14).
Show/hide table
Illustration 15 g03670108 - Retract the inner trailing edge adjusters (17) and outer trailing edge adjusters (16).
- Use inner trailing edge adjusters (17) to set the flatness of the trailing edge. Do not disturb outer trailing edge adjusters (16). Start at the second trailing edge adjuster in from each side and move to the center.
Show/hide table
Illustration 16 g03669955 - Loosen nut (18) on top of inner trailing edge adjusters (17) only. Turn the trailing edge adjuster counter-clockwise to retract the adjuster. Turn the trailing edge adjuster clockwise to extend the adjuster. Flatten the trailing edge of the main screed plate relative to Tool (A).
- Tighten nut (18).
- Remove tooling.
- Position plate (14) and secure with two bolts (15) and washers.
Show/hide table
Illustration 13 | g03719454 |
- Loosen bolts (20) and move indicator (21) to the zero mark on thickness scale (19). Tighten the bolts.
Show/hide table
Illustration 18 g03695774 - Loosen bolts (24) and move crown scale (23) so the zero mark aligns with pointer (22).
Show/hide table
Illustration 17 | g03671629 |
Caterpillar Information System:
415F2 Backhoe Loader Engine Oil and Filter - Change
MH3037 Material Handler Hydraulic System Swing Pump Air - Purge
950M, 962M, 950M Z and 962M Z Wheel Loaders Control Valve (Auxiliary) - Remove and Install
Inaccurate Hour Meter Reading on Electronic Monitoring System III (EMS III) Used on Certain Off-Highway Trucks{7478, 7490} Inaccurate Hour Meter Reading on Electronic Monitoring System III (EMS III) Used on Certain Off-Highway Trucks{7478, 7490}
824K Wheel Dozer, 825K Soil Compactor and 826K Landfill Compactor Machine Systems Transmission Oil Pump
980M and 982M Wheel Loaders Declaration of Conformity
980L Wheel Loaders Power Train, Steering, Braking, Hydraulic, and Machine Systems Drive Shaft
824K Wheel Dozer, 825K Soil Compactor and 826K Landfill Compactor Machine Systems Ride Control Accumulator
824K Wheel Dozer, 825K Soil Compactor and 826K Landfill Compactor Machine Systems Relief Valve (Brake Accumulator)
Procedure to Install 435-3715 Waste Handling Option Ar on Certain Wheel Loaders {0679, 7000, 7150, 7960} Procedure to Install 435-3715 Waste Handling Option Ar on Certain Wheel Loaders {0679, 7000, 7150, 7960}
415F2 Backhoe Loader Joystick Control - Loader
824K Wheel Dozer, 825K Soil Compactor and 826K Landfill Compactor Machine Systems Pressure Sensor
Procedure to Relocate the Circuit Breaker Group on the 797F Off-Highway Truck{0679, 1408, 1420, 1808, 5500, 5501, 7051} Procedure to Relocate the Circuit Breaker Group on the 797F Off-Highway Truck{0679, 1408, 1420, 1808, 5500, 5501, 7051}
415F2 Backhoe Loader Engine Oil Sample - Obtain
415F2 Backhoe Loader Engine Oil Level - Check
415F2 Backhoe Loader Belts - Inspect/Adjust/Replace
2014/08/18 New Engine Harness Routing {1408}
980M and 982M Medium Wheel Loaders Sensor Signal (Analog, Passive) - Test
980M and 982M Medium Wheel Loaders Sensor Signal (PWM) - Test
2014/03/27 A Procedure to Relocate the Circuit Breaker Group on the 797F Off-Highway Truck is Available {0679, 1408, 1420, 1808, 5500, 5501, 7051}
415F2 Backhoe Loader Fuel System Secondary Filter - Replace
980M and 982M Medium Wheel Loaders Sensor Supply - Test
826K Landfill Compactor, 825K Soil Compactor and 824K Wheel Dozer Engine Supplement Combustion Head - Remove and Install - Clean Emissions Module
980M and 982M Medium Wheel Loaders Solenoid Return - Test