Centershift Lock Bar and Front Frame Bushings - Install
Show/hide table
Required Tools | |||
Tool | Part Number | Part Description | Qty |
D | 1P-1834 | Bearing Puller Adapter | 1 |
4C-9633 | Puller Stud | 1 | |
9U-6833 | Nut | 1 | |
6V-3160 | Double Acting Cylinder | 1 | |
9U-6600 | Hand Hydraulic Pump | 1 | |
5P-8250 | Washer | 1 | |
E | 1P-1835 | Bearing Puller Adapter | 1 |
4C-9634 | Puller Stud | 1 | |
9U-6600 | Hand Hydraulic Pump | 1 | |
6V-3170 | Double Acting Cylinder | 1 | |
4K-0684 | Hard Washer | 1 | |
9U-6832 | Nut | 1 | |
F | 9U-6600 | Hand Hydraulic Pump | 1 |
6V-3160 | Double Acting Cylinder | 1 | |
4K-0684 | Hard Washer | 1 | |
1P-1838 | Bearing Puller Adapter | 1 | |
9U-6832 | Nut | 1 | |
4C-9634 | Puller Stud | 1 | |
7F-6068 | Sleeve | 1 | |
G | 1P-0510 | Driver Gp | 1 |
H | 183-3424 | Grease Cartridge | 1 |
- Lower the temperature of bushings (19) and use Tooling (F) in order to install bushings (19) in front frame assembly (20). Use a suitable lifting device to support Tooling (F).
Show/hide table
Illustration 2 g00935182 - Use Tooling (E) in order to install two bearings (16) in bar assembly (5). Install ring (17). Use Tooling (G) (not shown) in order to install seal (18).
Show/hide table
Illustration 3 g00935183 - Use Tooling (D) in order to install bearings (15).
Note: Install bearings to a depth of
9.53 ± 4.06 mm (0.375 ± 0.160 inch) below the outside faces of bar assembly (5). - Use Tooling (G) (not shown) in order to install seals (14).
- Repeat Step 3 and Step 4 for the opposite end of bar assembly (5).
Show/hide table
Illustration 4 g00935184 Show/hide tableIllustration 5 g00935178 - Attach a suitable lifting device to bar assembly (5). The weight of bar assembly (5) is approximately
204 kg (450 lb) . Position bar assembly (5) on the drawbar and yoke assembly. - Raise bar assembly (5) into position on the machine. Install pin (12) and washers (11).
Note: Use washers (11) in order to obtain a dimension of
2.29 ± 0.76 mm (0.090 ± 0.030 inch) between bar assembly (5) and front frame assembly (20). - Install lock (10) and bolts (9). Install cylinder (13).
- Apply Tooling (H) between inserts (5A) and ballstud (6A). Install cap (8) and install bolts (7).
Note: As required, use shims (7A) in order to allow the socket to move freely around ballstud (6A). Assemble the same quantity of shims (7A) on both sides of ballstud (6A).
- Start the engine and run the engine. Extend centershift cylinder (6) in order to raise bar assembly (5).
- Stop the engine.
- Remove the suitable lifting device.
Show/hide table
Illustration 6 g00935185 - Install pin (4) and washers (2).
Note: Use washers (2) in order to obtain a dimension of
2.29 ± 0.76 mm (0.090 ± 0.030 inch) between bar assembly (5) and front frame assembly (20). - Install lock (3) and bolts (1) .
Show/hide table
Illustration 1 | g00935181 |
End By:
- Install the centershift lock. Refer to Disassembly and Assembly, "Centershift Lock - Install".
Caterpillar Information System:
IT28G Integrated Toolcarrier and 924G, 924GZ and 928G Wheel Loaders MID 081 - CID 0590 - FMI 09
3512 and 3516 EUI Engines for 784B, 785B, 789B and 793B Off-Highway Trucks Engine Fan Speed Sensor
TH210 and TH215 Telehandlers Machine Systems Accumulator Charging Valve (Brake) - Remove
TH210 and TH215 Telehandlers Machine Systems Brake Accumulator - Remove and Install
R1300G Load Haul Dump 3306 Engine Supplement Flywheel
R1300G Load Haul Dump 3306 Engine Supplement Flywheel Housing
69D, 73D, 769C, 769D, 773B, 773D, 773E, 776B, 776C, 776D, 777B, 777C, 777D, 784B, 785, 785B, 789 and 793 Off-Highway Truck/Tractors and 771D, 775B, 775D and 775E Quarry Trucks Payload System Glossary of Terms
69D, 73D, 769C, 769D, 773B, 773D, 773E, 776B, 776C, 776D, 777B, 777C, 777D, 784B, 785, 785B, 789 and 793 Off-Highway Truck/Tractors and 771D, 775B, 775D and 775E Quarry Trucks Payload System Electronic Control Module (ECM) - Flash Program
14H Motor Grader Machine Systems Combination Valve - Install
533 and 543 Wheel Feller Bunchers Power Train Pump Drive - Install
69D, 73D, 769C, 769D, 773B, 773D, 773E, 776B, 776C, 776D, 777B, 777C, 777D, 784B, 785, 785B, 789 and 793 Off-Highway Truck/Tractors and 771D, 775B, 775D and 775E Quarry Trucks Payload System Electronic Control Module (ECM) - Replace
533 and 543 Wheel Feller Bunchers Power Train Pump Drive - Remove
2002/11/11 Correction to Systems Operation, Testing and Adjusting Module , "Main Relief Valve Test" {4095}
574B Forwarder Power Train Bogie
AP-1000D, AP-1055D, AP-655C, BG-2255C, BG-2455D and BG-260D Asphalt Pavers Caterpillar Monitoring System for AP Switches
CS-563E, CP-563E, CS-573E, CP-573E, CS-583E, CP-583E, CS-663E, CP-663E and CS-683E Vibratory Soil Compactors Hydraulic Tank Breather - Replace
RM-350B Reclaimer/Mixer Power Train Power Shift Transmission (Propel) - Assemble
424D, 428D and 438D Backhoe Loaders Operator Station
533 and 543 Wheel Feller Bunchers Power Train Bottom Guard (Rear Axle) - Remove and Install
574B Forwarder Power Train Oil Filter (Power Train Charging System)
533 and 543 Wheel Feller Bunchers Power Train Bottom Guard (Transmission) - Remove and Install
AP-655C and BG-2255C Asphalt Pavers Propel System Rotary Position Sensor (Brake Pedal) - Test and Adjust
TK711, TK721, TK722 and TK732 Track Feller Bunchers Hydraulic System Piston Pump (Disc Saw) - Test and Adjust
TK711, TK721, TK722 and TK732 Track Feller Bunchers Hydraulic System Piston Motor (Disc Saw) - Test and Adjust