UPS 120, UPS 150, UPS 250 and UPS 300 Uninterruptible Power Supplies Caterpillar


Electrical Connections

Usage:

UPS 250 APZ

AC Power Wiring Connections

Determine the AC currents for your system based on kVA, voltage, and installed options. Also refer to equipment nameplates for the model number, rating, and voltage.


NOTICE

All Power connections must be completed by a licensed electrician that is experienced in wiring the UPS type of equipment. Wiring must be installed in accordance with the National Electrical Code (NEC) and all applicable local. Improper wiring may cause equipment damage or injury to personnel. Verify that all incoming high and low voltage power circuits are de-energized. Verify that all incoming high and low voltage power circuits locked out before installing cables or making electrical connections.


The UPS is designed for the cables to enter the cabinet top or bottom. Removable access plates must be cut in order to accommodate the conduit size. Input cables and output cables must be run in separate conduits.

The connection terminals are drilled for 1/2 inch hardware and spaced for one or two hole NEMA lugs.

Connection terminals can be oriented for top entry or bottom entry. Orienting the terminals in the direction of cable entry will minimize the number of bends in the cables. Space limitations require smaller cables installed parallel to one another. The use of smaller cables reduces the risk of damage to the unit or the cables while pulling the cables.

Note: The lugs and the cables are not supplied. Refer to "NEC Article 210-19" and the "NEC Table 310-16" for the correct size of the cables. Refer to "NEC Article 250-95" for the correct size of the ground. Refer to "NEC Article 310-15" for the correct size of the neutral.

The torque for the wire connections is 61 N·m (45 lb ft).

Note: A service disconnect device must be installed. The disconnect device must be rated properly for the output power. The disconnect device is not supplied.

  1. The following wires and cables must be housed in an individual, separate conduit or cable tray. Placing multiple cables in the same conduit with other control or power wiring may cause the system to fault.

    • All shielded cables

    • Non-shielded cables

    • Non-shielded control wires

    • Non-shielded remote control wires

  2. Verify that utility power and overcurrent protection ratings will accommodate the UPS input rating.

  3. A safety ground wire must be installed from building ground to the ground point in the UPS module cabinet. The grounding conductor must comply with the following conditions of installation.

    1. The insulated grounding conductor must be sized in accordance with the NEC, in the USA, and all other local and national codes. The insulated grounding conductor must be installed as part of the branch circuit that supplies power to the unit or system.

    2. The grounding conductor must have an earth ground at the service equipment. If the system is supplied by a separately derived system, the grounding conductor must have an earth ground at the supply transformer or generator set.

  4. Attachment plug receptacles used in the vicinity of the unit or system must be grounding type. The grounding conductors serving the attachment plug receptacles are to be connected to earth ground at the service equipment.

  5. Observe clockwise phase rotation of all power wiring. Phase A leads, Phase B leads, and Phase C leads. The phase rotation must be confirmed by a qualified electrician.

    Note: The weight of the power cables must be supported adequately to avoid stress on the bus bars and lugs.

  6. The installing contractor can remove the access plates from the top or bottom of the cable access areas of the UPS in order to cut entry holes for conduit.


    NOTICE

    After cutting holes in the access plates, ensure that no foreign matter such as metal shavings, sawdust, insulation, or wire fragments remain inside the UPS. Be certain to plug any unused holes in the plates through which foreign matter could enter the UPS.


  7. The following three-phase power cables are connected in the bypass cabinet:

    • Input cables

    • Output cables

    • Ground cables

    • Neutral cables

    Note: Neutral cables are used only in four-wire systems.

The Underwriters Laboratories requires that the UPS system must be installed with an appropriately rated service disconnect device. The disconnect device must be rated for the output power. The disconnect device is not supplied with the UPS. If required by local and/or national regulations, an appropriately rated service disconnect device for input and output power must be provided.

The three-phase AC input and three-phase AC output cables are connected to a copper plated bus bar. The holes are spaced for two hole NEMA lugs with barrels.

The ground cable is connected to a copper plated bus bar. The bus bars are drilled for 3/8 inch hardware. The holes are spaced for two hole NEMA lugs with barrels.

The tab on the copper plated bus bar must be inverted in order for the cable to be installed from the bottom of the cabinet.

Overcurrent protection must be provided externally to the UPS. Overcurrent protection must conform to local and national codes.

Use 75° C (167° F) wire.

Recommended wire sizes are based on NFPA 70, NEC 2002 Edition. Local, national, or other applicable codes must also be observed. Compliance with all codes is the responsibility of the installer.

Cable Connection

Ensure that proper phase rotation is maintained at all times.

  1. Route the AC power cables through the holes that are intendedto be usedfor the entry of the cables. The holes are punched in the galvanized steel panel.

  2. Connect the three phase AC input cables to the bus tab that is for power distribution. The bus tab is located in the bypass cabinet. Torque the fasteners for the cables to 61 N·m (45 lb ft).

  3. Connect the three phase AC output cables to the bus tab that is for power distribution. The bus tab is located in the bypass cabinet. Torque the fasteners for the cables to 61 N·m (45 lb ft).

  4. Connect the ground cable to the copper plated bus tab that is located in the termination cabinet. Torque the fasteners for the ground cable to 61 N·m (45 lb ft).

Control Wiring


NOTICE

Control wiring must be stranded. Control wiring must be installed in steel conduit that is used only for control wiring. Control wiring must be separated from power wiring. Route control wiring as far away from power cables as possible to minimize Electromagnetic Interference (EMI).


Customer interfaces are accessible through dry contacts on the system input/output (SIO) board (2). The SIO board (2) is located in the left component panel in the UPS cabinet. The UPS has a total of six input contacts and six "form C" output contacts available for customer use. The UPS also accepts serial connection for monitoring and control.

UPS Interface Board Locations



Illustration 1g02836417
(1) Left component panel
(2) SIO board
(3) SOID board
(4) Access panel screw
(5) Access panel
(6) Access panel screw

The access panel (5) must be removed to access the dry contact in the UPS cabinet. Remove the access panel screws to remove the access panel. The dry contacts are located on the SIO board that is located on the left component panel.



Illustration 2g02836480
Typical system input/output (SIO) board
(10) J7 Remote emergency power off (EPO) contacts
(11) J14 Remote Input Contacts
(12) J6 Remote Output Contacts
(13) J12 Device Net
(14) J16 Modem DB 9
(15) J10 Modem RJ45
(16) J10a Modem RJ11
(17) J9 Ether Net
(18) J1 RS-232/ RS-485 9 pin connector
(19) J8 UPSNET/CAN A
(20) J4 24 VDC Power in

The connections for a typical system input/output (SIO) board are shown in Illustration 2.



Illustration 3g02836481
SIO daughter board
(25) J4 24 VDC power In
(26) J1 RS-485
(27) J5 Remote panel out
(28) J8 Backup UPS NET


Illustration 4g02836482
J7 contacts for the REPO
(30) J7
(31) Jumper

The REPO contacts allow for connection of a button external to the UPS. The REPO button is equivalent to the local emergency power off button. The REPO contacts (J7) are located on the SIO board.

Note: The J7 terminal has two sets of contacts that operate independently of each other. Terminals 1 and 3 are normally open. Terminals 2 and 4 are normally closed.

Note: The UPS is shipped with a jumper connected across the normally closed contacts, terminals 2 and 4. If the normally closed contacts are used, remove the jumper. If the normally open contacts, terminals 1 and 3, are used, do not remove the jumper.


NOTICE

When the REPO button is used, high voltage may still be present on the input terminals. Customer supplied input breakers may or may not be disabled. The REPO button circuit is considered an "Extra-Low Voltage" (EVL) control circuit. The wiring must be routed separately from the Class 2 "Safety Extra-Low Voltage" (SELV) wiring. Use NEC Class 1 wiring methods. A dedicated conduit is required.


SIO Board Connections

Table 1
From Customer Optional Monitoring Interface  To UPS Cabinet  Connection Type  Wire Type  Description 
  SIO board J1  DB9 (female)  nine wire serial cable  Monitoring Data(1) 
  SIO board J9  RJ45 8-pin  Cat 5, 4 pair UTP 24 AWG (unshielded)  Ethernet (1)(2) 
  SIO board J14-7  Terminal Block  24-12 AWG, twisted Pair  Input 1 relay coil (-) (1)(2)(3) 
  SIO board J14-1  Terminal Block  24-12 AWG, twisted Pair  Ground (1)(2)(3) 
  SIO board J14-8  Terminal Block  24-12 AWG, twisted Pair  Input 2 relay coil (-) (1)(2)(3) 
  SIO board J14-2  Terminal Block  24-12 AWG, twisted Pair  Ground (1)(3) 
  SIO board J14-9  Terminal Block  24-12 AWG, twisted Pair  Input 3 relay coil (-) (1)(2)(3) 
  SIO board J14-3  Terminal Block  24-12 AWG, twisted Pair  Ground (1)(2)(3) 
  SIO board J14-10  Terminal Block  24-12 AWG, twisted Pair  Input 4 relay coil (-) (1)(2)(3) 
  SIO board J14-4  Terminal Block  24-12 AWG, twisted Pair  Ground (1)(2)(3) 
  SIO board J14-11  Terminal Block  24-12 AWG, twisted Pair  Input 5 relay coil (-) (1)(2)(3) 
  SIO board J14-5  Terminal Block  24-12 AWG, twisted Pair  Ground (1)(2)(3) 
  SIO board J14-12  Terminal Block  24-12 AWG, twisted Pair  Input 6 relay coil (-) (1)(2)(3) 
  SIO board J14-6  Terminal Block  24-12 AWG, twisted Pair  Ground (1)(2)(3) 
  SIO board J6-1  Terminal Block  24-12 AWG, twisted Pair  Output 1 N.O.(1)(2)(3) 
  SIO board J6-2  Terminal Block  24-12 AWG, twisted Pair  Common (1)(2)(3) 
  SIO board J6-3  Terminal Block  24-12 AWG, twisted Pair  Output 1 N.C. (1)(2)(3) 
  SIO board J6-4  Terminal Block  24-12 AWG, twisted Pair  Output 2 N.O. (1)(2)(3) 
  SIO board J6-5  Terminal Block  24-12 AWG, twisted Pair  Common (1)(2)(3) 
  SIO board J6-6  Terminal Block  24-12 AWG, twisted Pair  Output 2 N.C. (1)(2)(3) 
  SIO board J6-7  Terminal Block  24-12 AWG, twisted Pair  Output 3 N.O. (1)(2)(3) 
  SIO board J6-8  Terminal Block  24-12 AWG, twisted Pair  Common (1)(2)(3) 
  SIO board J6-9  Terminal Block  24-12 AWG, twisted Pair  Output 3 N.C. (1)(2)(3) 
  SIO board J6-10  Terminal Block  24-12 AWG, twisted Pair  Output 4 N.O. (1)(2)(3) 
  SIO board J6-11  Terminal Block  24-12 AWG, twisted Pair  Common (1)(2)(3) 
  SIO board J6-12  Terminal Block  24-12 AWG, twisted Pair  Output 4 N.C. (1)(2)(3) 
  SIO board J6-13  Terminal Block  24-12 AWG, twisted Pair  Output 5 N.O. (1)(2)(3) 
  SIO board J6-14  Terminal Block  24-12 AWG, twisted Pair  Common (1)(2)(3) 
  SIO board J6-15  Terminal Block  24-12 AWG, twisted Pair  Output 5 N.C. (1)(2)(3) 
  SIO board J6-16  Terminal Block  24-12 AWG, twisted Pair  Output 6 N.O. (1)(2)(3) 
  SIO board J6-17  Terminal Block  24-12 AWG, twisted Pair  Common (1)(2)(3) 
  SIO board J6-18  Terminal Block  24-12 AWG, twisted Pair  Output 6 N.C. (1)(2)(3) 
  SIO board J7-1  Terminal Block  24-12 AWG, twisted Pair  Remote EPO Ground (1)(4) 
  SIO board J7-2  Terminal Block  24-12 AWG, twisted Pair  Remote EPO Ground (1)(4)(5) 
  SIO board J7-3  Terminal Block  24-12 AWG, twisted Pair  Remote EPO N.O. (1)(4) 
  SIO board J7-4  Terminal Block  24-12 AWG, twisted Pair  Remote EPO N.C.(1)(4)(5) 
(1) Cables not supplied
(2) Suitable for connections to NEC Class 2/SELV circuits only.
(3) Programmable discrete signals.
(4) Use NEC Class 1/ELV wiring methods.
(5) Remove factory jumper to use these terminals.

Dry Contacts

Use the following steps to access the dry contacts:

  1. Open the system cabinet doors.

  2. The dry contacts are located on the SIO board on the left component panel.

All contacts can be configured with UPSView to indicate if certain conditions exist. Each input is intended to interface to a single-pole single-throw switch. The switch connects the pair of contacts or the switch disconnects the pair of contacts. The contacts that are user programmable have an operating parameter that is used to configure that contact.

The following list of functions can be assigned to the contacts for the remote input block. Assigning functions are done by entering the parameter in the operating parameter field for the associated remote input.

Table 2 shows the function list for the input contacts.

Table 2
Function List for Input Contact 
Function  Description 
Disabled - No function 
On Genset - When the "On Genset" function is activated, operational settings can be made for transient voltage detection, maximum input current, and walk-in rate. 
Remote Bypass - Remote switch of UPS to bypass. 
Remote Online - Remote switch of the UPS to on-line condition - only if no errors are active. 
Building Alarm 1 - an external alarm output contact is triggered. 
Building Alarm 2 - an external alarm output contact is triggered. 
Building Alarm 3 - an external alarm output contact is triggered. 
Building Alarm 4 - an external alarm output contact is triggered. 
Fire Alarm - an external alarm output contact is triggered. 
Remote Silence - silences the buzzer, a notice, or alarm that is active. 
10  Genset Breaker Open - prints a breaker open message when the input is activated and a breaker closed message when the input is deactivated. 
11  Abnormal Room Temperature - prints a message indicating that the input is activated or deactivated. 
12  Synchronize to the external source 
13  User Notice Message 1 - used to configure the user text messages displayed by UPSView. 
14  User Notice Message 2 - used to configure the user text messages displayed by UPSView. 
15  User Alarm Message 1 - used to configure the user text messages displayed by UPSView. 
16  User Alarm Message 2 - used to configure the user text messages displayed by UPSView. 
17  User Normal Message 1 - generates event status 
18  User Normal Message 2 - generates event status 
19  GSO Group A Open - Monitors the status of any installed GenStart Module 
20  GSO Group B Open - Monitors the status of any installed GenStart Module 
21  GSO Group C Open - Monitors the status of any installed GenStart Module 
22  GSO Group D Open - Monitors the status of any installed GenStart Module 
23  Remote Spin Down - Initiates UPS bypass spin down 

Table 3 shows the default function.

Table 3
Default Function Assignments for Input Contacts 
Contact  Function  Description 
On Generator 
Remote switch from UPS to Bypass 
Remotely switch the UPS to online status - Remote switching is done only if there are no errors active. 
Building Alarm 1 
Building Alarm 2 
Building Alarm 3 

Table 4 shows the function list for the output contacts.

Table 4
Function List for Output Contacts 
Function   Description 
No function 
1-100  Flywheel Percent Energy - the flywheel has the programmed percentage of usable energy available and the system is online. 
101  Online (normal) 
102  On Bypass 
103  Flywheel Discharging 
104  A notice condition on an alarm condition is active. 
105  Alarm condition is active. 
106  Overload 
107  Cabinet over temperature 
108  External Alarm - External alarm is activated by programming remote inputs to any of the building alarms or the fire alarm functions. 
109  GSC unavailable 
110  Overload Bypass - The system is in bypass because of an overload condition. 
111  Fusible Link Error - The fusible link for the DC bus capacitor is open. 
112  Fan Error 
113  Run Genset - Used with generator start unit. Enables manual start. 
114  Pulsed Start Genset - Used with generator start unit. Enables manual start. 
115  Pulsed Stop Genset - Used with generator start unit. Enables manual stop. 
116  ATS Command - Used with operating parameter ATS command level. When in discharge and when total available system energy drops below preset level, the contact closes. 
117  Motoring 

Table 5 shows the default function assignments for output contacts.

Table 5
Default Function Assignments for Output Contacts 
Contact  Function  Description 
101  Online (normal) 
102  On Bypass 
103  Flywheel Discharging 
50  Flywheel Percent Energy 
104  Notice condition or an Alarm condition is active 
105  Alarm condition is active 

Caterpillar Information System:

Back to top
The names Caterpillar, John Deere, JD, JCB, Hyundai or any other original equipment manufacturers are registered trademarks of the respective original equipment manufacturers. All names, descriptions, numbers and symbols are used for reference purposes only.
CH-Part.com is in no way associated with any of the manufacturers we have listed. All manufacturer's names and descriptions are for reference only.