Front Axle Group - Install
Installation Procedure
Show/hide table
Required Tools     | |||
---|---|---|---|
Tool     | Part Number     | Part Description     | Qty     |
A     | 1U-9745     | Jack     | 1     |
B     | 6V-6146     | Load Levelers     | 1     |
Show/hide table
Personal injury or death can result from improper lifting or blocking. When a hoist or jack is used to lift any part or component, stand clear of the area. Be sure the hoist or jack has the correct capacity to lift a component. Install blocks or stands before performance of any work under a heavy component. Approximate weights of the components are shown. Clean all surfaces where parts are to be installed. |
- Use Tooling (A) and Tooling (B) to install fixed axle (4) to the front of the machine. Weight of the fixed axle is 379 kg (835 lb).
- Install plates, washers, eight bolts (3), and nuts to the fixed axle. Tighten the bolts.
Show/hide table
Illustration 1 | g00647504 |
- Connect line (2) and line (1) to the fixed axle.
Show/hide table
Illustration 2 | g00652500 |
Show/hide table
Illustration 3 | g00652486 |
Note: Step 3 is for the 908.
Show/hide table
Illustration 4 | g00647496 |
- Remove Tooling (B) and Tooling (A) from the fixed axle.
End By:
- Install the tire and rim. Refer to Disassembly and Assembly, "Tire and Rim - Remove and Install".
- Install the parking brake for the 908. Refer to Disassembly and Assembly, "Parking Brake - Remove and Install".
- Install the service and parking brake for the 906. Refer to Disassembly and Assembly, "Service and Parking Brake - Remove and Install".
- Install the drive shaft. Refer to Disassembly and Assembly, "Drive Shaft - Remove and Install".
- Separate the steering frame lock. Refer to Disassembly and Assembly, "Steering Frame Lock - Separate and Connect".
Caterpillar Information System:
906, 907 and 908 Compact Wheel Loaders Power Train Front Axle Group - Remove
854K Wheel Dozer Machine Systems Gear Pump (Steering Oil Cooler) (Steering Pilot) - Install
854K Wheel Dozer Machine Systems Gear Pump (Steering Oil Cooler) (Steering Pilot) - Remove
854K Wheel Dozer Machine Systems Piston Pump (Steering) - Install
854K Wheel Dozer Machine Systems Piston Pump (Steering) - Remove
Installation Procedure for Secondary Pin Retention System on Wheel Loaders{6107, 6118} Installation Procedure for Secondary Pin Retention System on Wheel Loaders{6107, 6118}
938H Wheel Loader and IT38H Integrated Toolcarrier Hydraulic System Main Control Valve
Procedure to Repair the Mainframe on Certain Track-Type Tractors{7050} Procedure to Repair the Mainframe on Certain Track-Type Tractors{7050}
854K Wheel Dozer Machine Systems Piston Pump (Steering) - Assemble
854K Wheel Dozer Machine Systems Piston Pump (Steering) - Disassemble
992K Wheel Loader Machine Systems Piston Pump (Implement, Center) - Install
992K Wheel Loader Machine Systems Piston Pump (Implement, Center) - Remove
906, 907 and 908 Compact Wheel Loaders Power Train Service and Parking Brake (Standard Axle) - Remove
Functionality for the Dual Tilt on the D9R and D9T{5104} Functionality for the Dual Tilt on the D9R and D9T{5104}
Procedure to Rework Loader Buckets for Use with Fusion Couplers {6001, 6129, 6434} Procedure to Rework Loader Buckets for Use with Fusion Couplers {6001, 6129, 6434}
992K Wheel Loader and 854K Wheel Dozer Power Train Torque Converter (Lockup)
994F Wheel Loader Power Train Fixed Axle (Front) - Remove
938H Wheel Loader and IT38H Integrated Toolcarrier Power Train Features
IT38H Integrated Toolcarrier and 938H Wheel Loader Transmission Electronic Control System MID 081 - CID 0368 - FMI 02
992K Wheel Loader Electrohydraulic System Electrical System Schematic
IT38H Integrated Toolcarrier and 938H Wheel Loader Transmission Electronic Control System MID 081 - CID 0590 - FMI 14
2008/01/21 A New Lubricator for the Air Starting Motor is Available {1451}
IT38H Integrated Toolcarrier and 938H Wheel Loader Transmission Electronic Control System Switch Circuits
2007/11/26 A New Sun Gear Assembly and a New Carrier are Now Used {4011}