To facilitate removal of the bucket pins without causing damage to the pins, the bearings, and/or the O-ring seals put the bucket on the floor and the stick in a vertical position, as shown. |
- Position the bucket, the stick and the bucket control linkage on the ground.
Show/hide table
Illustration 1 g00534630 Note: Relieve the pressure on the bucket pins by moving the stick up and down.
Show/hide tableIllustration 2 g00880305 - Remove the nuts and retaining bolt (5) and remove bucket pin (4).
- Pull link assembly (1) away from the bucket. Remove two O-ring seals (3).
- Remove the nuts and retaining bolt (2).
Show/hide table
Illustration 3 g01517271 - Remove nuts (6) and retaining bolt (7).
- Remove pin (8) and the O-ring seals. Separate the stick from bucket (9).
Note: The weight of the bucket (9 ) is approximately
240 kg (530 lb) .
Show/hide table
Required Tools | |||
Tool | Part Number | Part Description | Qty |
A | 5P-0960 | Grease Cartridge | 1 |
Note: Make sure that the stick pin bore, the bucket pin bores, the bucket pins, the flange and the O-ring seals are thoroughly clean prior to installation of the bucket.
Note: Check the condition of the O-ring seals. If the O-ring seals are worn or damaged, use new parts for replacement.
- Lower the stick into bucket (9) and align the pin bores. Move the bucket until one side of the bucket makes contact with the stick. Measure the clearance between the bucket and the stick.
- Apply Tooling (A) on bucket pin (8). Install bucket pin (8) and the O-ring seals. Align the retaining bolt hole in the bucket pin with the retaining bolt hole in the bucket. Install retaining bolt (7) and nuts (6).
Show/hide table
Illustration 5 g00880305 - Align the pin bore in link assembly (1) with the pin bores in the bucket.
- Apply Tooling (A) on bucket pin (4). Install bucket pin (4) and O-ring seals (3).
- Align the retaining bolt hole in the bucket pin with the retaining bolt hole in the bucket. Install retaining bolt (5) and the nuts.
Show/hide table
Illustration 6 g00357378 - Use the following procedure in order to tighten all the nuts:
- Position the outside nut even with the end of the retaining bolt or
0.5 mm (0.02 inch) beyond the end of the retaining bolt. - Tighten the inside nut against the outside nut to a torque of
70 ± 15 N·m (50 ± 10 lb ft) .
- Position the outside nut even with the end of the retaining bolt or
- Lubricate the bucket control linkage. Refer to Operation and Maintenance Manual, SEBU7421, "Bucket Linkage - Lubricate" for the correct procedure.
Show/hide table
Illustration 4 | g01517271 |
Note: The weight of the bucket (9 ) is approximately
Caterpillar Information System:
415F2, 416F2, 420F2 IT, 420F2 ST, 430F2 IT and 430F2 ST Backhoe Loaders Power Train Drive and Steering Axle (Front) - Remove
415F2, 416F2, 420F2 IT, 420F2 ST, 430F2 IT and 430F2 ST Backhoe Loaders Power Train Steering Cylinder (Front) - Remove and Install
308E Mini Hydraulic Excavator Machine Systems Blade Cylinder - Remove and Install
M318F, M320F and M322F Wheeled Excavators Hydraulic System Pilot Pump (High Pressure Cutoff) - Test and Adjust
M318F, M320F and M322F Wheeled Excavators Hydraulic System Pilot Pump (Maximum Displacement) - Test
M318F, M320F and M322F Wheeled Excavators Hydraulic System Pilot Pump (Minimum Displacement) - Test
308E Mini Hydraulic Excavator Engine Supplement Fan and Fan Drive - Remove
320D2 Forest Machine Machine System Specifications Protection Guard
320D2 Forest Machine Machine System Specifications Hydraulic Tank and Filter
320D2 Forest Machine Machine System Specifications Stick - 2.92 m (9.580 ft)
335F CR Excavator Machine Systems Gear Pump (Pilot) - Remove and Install
335F CR Excavator Machine Systems Swivel - Remove and Install
Installation Procedure for the 377-8018 Control Module Gp on Certain Hydraulic Excavators{1901} Installation Procedure for the 377-8018 Control Module Gp on Certain Hydraulic Excavators{1901}
320D and 323D Excavators Machine System Specifications Swing Motor
320D2 Forest Machine Machine System Specifications Boom Lines
320D2 Forest Machine Machine System Specifications Fuel Tank
320D2 Forest Machine Machine System Specifications Boom Lighting
320D2 Forest Machine Machine System Specifications Cab Riser Wiring
320D2 Forest Machine Machine System Specifications Cab Riser Wiring
320D2, 323D2, 326D2, 329D2 and 330D2 Excavators Tool Control System System 3 Prime: Default Value of Work Tool Parameters
320D2 Forest Machine Machine System Specifications Control Valve
415F2, 416F2, 420F2 IT, 420F2 ST, 430F2 IT and 430F2 ST Backhoe Loaders Power Train Axle Housing and Flange - Remove
320D2, 323D2, 326D2, 329D2 and 330D2 Excavators Tool Control System System 3 Prime: Relief Valve (Line) - Test and Adjust - Auxiliary Control Valve
Quick Coupler Installation Status{7610, 7620} Quick Coupler Installation Status{7610, 7620}