325C LCR Excavator Hydraulic System Caterpillar


Boom Hydraulic System

Usage:

325C BKW

Boom Raise (High Speed)




Illustration 1g01155491

Hydraulic schematic for BOOM RAISE (high speed)

(1) Boom cylinders

(2) Line (oil flow from boom cylinder rod end)

(3) Line (oil flow to boom cylinder head end)

(4) Valve

(5) Boom drift reduction valve

(6) Return line

(7) Port

(8) Parallel feeder passage

(9) Return passage

(10) Line

(11) Main control valve

(12) Passage

(13) Check valve

(14) Load check valve

(15) Port

(16) Boom II control valve

(17) Parallel feeder passage

(18) Return passage

(19) Boom I control valve

(20) Port

(21) Pilot line

(22) Pilot control valve (boom and bucket)

(23) Pilot line

(24) Pilot line

(25) Pilot line

(26) Pressure reducing valve for boom priority

(27) Left pump

(28) Right pump

(29) Pilot pump

(33) Spring

(37) Spring

A BOOM RAISE operation at high speed is accomplished when the oil delivery from both left pump (27) and right pump (28) is supplied to the head end of boom cylinders (1). Boom I control valve (19) and boom II control valve (16) operate during the high speed operation. A BOOM RAISE operation at low speed is accomplished when the oil delivery from only right pump (28) is supplied to the head end of boom cylinders (1). During the low speed operation, boom I control valve (19) operates alone.




Illustration 2g01159623

Main control valve compartment

(16) Boom II control valve

(19) Boom I control valve




Illustration 3g00694273

Boom drift reduction valve (bottom view)

(5) Boom drift reduction valve

The oil delivery from right pump (28) flows through parallel feeder passage (17) in main control valve (11) to boom I control valve (19). The oil delivery from left pump (27) flows through parallel feeder passage (8) in main control valve (11) to boom II control valve (16) .

When the joystick for the boom is moved to the full BOOM RAISE position, the pilot oil flows from pilot control valve (22) through pilot line (24). The pilot oil flow then divides into two flow paths. Part of the pilot oil flows through pilot line (21) to port (7) of main control valve (11). The remainder of the pilot oil flows through pilot line (23) to port (20) of the main control valve.

A portion of the oil in pilot line (23) also flows through pilot line (25) to the pressure reducing valve for boom priority (26). During a combined operation of BOOM RAISE and STICK IN, the pilot oil flow to the pressure reducing valve for boom priority (26) causes the boom circuit to receive oil flow priority. This allows the boom to raise at a high speed.




Illustration 4g00747467

Boom I control valve (BOOM RAISE position)

(14) Load check valve

(17) Parallel feeder passage

(18) Return passage

(20) Port

(30) Port

(31) Passage

(32) Passage

(33) Spring

(34) Passage

(35) Spool

The pilot oil flow from port (20) shifts spool (35) of boom I control valve (19) against the force of spring (33). The oil delivery from the right pump in parallel feeder passage (17) flows through load check valve (14), passage (31), passage (34) and port (30) to boom drift reduction valve (5). The oil delivery from the right pump shifts valve (4) in boom drift reduction valve (5) to the right. The oil delivery from the right pump then flows through line (3) to the head end of boom cylinders (1) .

Note: For more information on the boom drift reduction valve, refer to Systems Operation, "Boom Drift Reduction Valve".




Illustration 5g00827976

Boom II control valve (BOOM RAISE position)

(7) Port

(8) Parallel feeder passage

(13) Check valve

(15) Port

(36) Passage

(37) Spring

(38) Spool

(39) Passage

The pilot oil flow in port (7) of boom II control valve (16) shifts spool (38) against the force of spring (37). The oil delivery from the left pump in parallel feeder passage (8) now flows through passage (36), passage (39), check valve (13) and flows out of port (15) to line (10). The oil delivery from the left pump combines with the oil delivery from the right pump at boom drift reduction valve (5). The combined pump oil flows through passage (12) and line (3) to the head end of boom cylinders (1) .

Note: The swing priority valve does not affect the boom II control valve.

Return oil from the rod end of boom cylinders (1) flows through line (2) to boom I control valve (19). The oil then flows through passage (32), return passage (18), return passage (9) and return line (6) to the hydraulic tank.

Boom Raise (Low Speed)

When the joystick for the boom is moved less than half of the travel distance for BOOM RAISE, low pilot oil pressure is supplied to boom I control valve (19) and boom II control valve (16) .

When the boom is raised at a low speed, boom I control valve (19) opens and boom II control valve (16) remains closed. The force of spring (33) in boom I control valve (19) is less than the force of spring (37) in boom II control valve (16). Because of the low pilot oil pressure, boom I control valve (19) will open and boom II control valve (16) will remain closed.

The oil delivery from right pump (28) now flows to the head end of boom cylinders (1). Without the oil delivery from left pump (27), the cylinder rod movement slows down when the boom is raised. The low speed operation of the boom is performed.

Boom Priority




Illustration 6g01158549

Hydraulic schematic for BOOM RAISE and STICK IN

(1) Boom cylinders

(22) Pilot control valve (boom and bucket)

(26) Pressure reducing valve for boom priority

(40) Stick II control valve

(41) Pilot control valve (stick and swing)

During combined operations of BOOM RAISE and STICK IN, the pilot oil pressure from the pilot control valve for the boom (22) activates the pressure reducing valve for boom priority (26). The pressure reducing valve for boom priority (26) causes oil flow priority to the head end of the boom cylinders (1) during this combined hydraulic operation.

When the joystick for the stick is moved to the STICK IN position, a portion of the pilot oil from the pilot control valve for the stick (41) flows through the pressure reducing valve for the boom priority (26) to the stick II control valve (40). As the joystick for the boom is moved farther from the NEUTRAL position during a BOOM RAISE operation, pilot oil pressure from the pilot control valve for the boom (22) increases. This gradual increase in pilot oil pressure causes the spool in the pressure reducing valve for the boom priority (26) to gradually shift.

A portion of the pilot oil that flows to stick II control valve (40) from the pilot control valve for the stick (41) is routed to the hydraulic tank. The pilot oil pressure that acts on stick II control valve (40) decreases. Stick II control valve (40) shifts toward the NEUTRAL position. The amount of oil flow from the main pumps to the stick hydraulic circuit decreases. This causes a greater portion of the oil flow from the main pumps to flow to the head end of the boom cylinders (1) .

Since the pilot oil pressure from the pilot control valve for the boom (22) directly corresponds to the amount of movement or position of the joystick a gradual change to boom priority occurs. Thus, boom priority is controlled by the position of the joystick for the boom and boom priority automatically activates when the joystick reaches a certain position during a BOOM RAISE operation.

Boom Lower




Illustration 7g01159245

Hydraulic schematic for BOOM LOWER

(1) Boom cylinders

(2) Line (oil flow to boom cylinder rod end)

(3) Line (oil flow from boom cylinder head end)

(4) Valve

(5) Boom drift reduction valve

(14) Load check valve

(16) Boom II control valve

(17) Parallel feeder passage

(18) Return passage

(19) Boom I control valve

(22) Pilot control valve (boom and bucket)

(27) Left pump

(28) Right pump

(29) Pilot pump

(33) Spring

(40) Orifice

(41) Boom regeneration valve

(42) Port

(43) Orifice

(44) Negative flow control line

(45) Center bypass passage

(46) Port

(48) Valve

(49) Passage

(50) Drain line

(51) Passage

(52) Pilot line

(53) Pilot line

During a BOOM LOWER operation, the oil delivery from only right pump (28) is supplied to boom cylinders (1) through boom I control valve (19). Boom I control valve (19) operates alone. Boom II control valve (16) is not operational in the BOOM LOWER operation.

The BOOM LOWER operation contains a regeneration circuit. When the joystick for the boom is moved to the BOOM LOWER position, orifice (43) in boom I control valve (19) and boom regeneration valve (41) are operational in the boom hydraulic circuit. The return oil flow from the head end of boom cylinders (1) flows through boom regeneration valve (41) to the rod end of the boom cylinders. The boom regeneration valve is described later in this section.

When the joystick for the boom is moved to the BOOM LOWER position, pilot oil from pilot control valve (22) flows through pilot line (52). The pilot oil flow then divides into three flow paths. Part of the pilot oil flows through port (46) to boom I control valve (19). Part of the pilot oil flows through port (42) to boom regeneration valve (41). The remainder of the pilot oil flows through pilot line (53) of boom drift reduction valve (5) .

Since the pilot oil pressure has caused the spool in boom I control valve (19) to shift against the force of spring (33), the oil delivery from the right pump that flows through center bypass passage (45) is restricted by orifice (43). The negative flow control pressure in negative flow control line (44) decreases. The right pump upstrokes because of the negative flow control operation.

Reference: For more information concerning the negative flow control operation, refer to Systems Operation, "Negative Flow Control".




Illustration 8g00904282

Boom I control valve (BOOM LOWER position)

(14) Load check valve

(17) Parallel feeder passage

(18) Return passage

(30) Port

(32) Port

(33) Spring

(35) Spool

(42) Orifice

(45) Orifice

(46) Port

(49) Passage

The pilot oil flow from port (46) shifts spool (35) in boom I control valve (19) against the force of spring (33). The oil delivery from the right pump in parallel feeder passage (17) flows through load check valve (14), passage (49) and port (32). The oil delivery from the right pump then flows through line (2) to the rod end of boom cylinders (1) .

The return oil from the head end of boom cylinders (1) flows through line (3) into boom drift reduction valve (5). Since valve (48) is shifted by the pilot pressure from pilot line (53), passage (49) is open to drain line (50). The return oil pressure shifts valve (4) to the right. The return oil in line (3) enters passage (51) .

A portion of the return oil flows into port (30) of boom I control valve (19). The return oil flow is restricted by orifice (40). The return oil pressure in passage (51) increases. Most of the return oil flows through boom regeneration valve (41). The return oil is now supplied to the rod end of the boom cylinders through line (2) .

Boom Regeneration Valve




Illustration 9g00904285

Boom regeneration valve (slow boom down)

(11) Main control valve

(42) Pilot port

(56) Passage

(57) Check valve

(58) Spool (boom regeneration valve)

(59) Passage




Illustration 10g00904286

Boom regeneration valve (fast boom down)

(11) Main control valve

(42) Pilot port

(56) Passage

(57) Check valve

(58) Spool (boom regeneration valve)

(59) Passage

The boom hydraulic circuit contains a regeneration circuit. This regeneration circuit allows the return oil from the head end of the boom cylinders to be supplied to the rod end of the boom cylinders during the BOOM LOWER operation.

When the joystick for the boom is moved to the BOOM LOWER position, pilot oil flow from the pilot control valve (boom and bucket) enters pilot port (42). Spool (58) in the boom regeneration valve shifts downward. The return oil from the head end of the boom cylinders flows through passage (59) and through the throttling slots on the spool for the boom regeneration valve to check valve (57). Check valve (57) opens and the return oil flows through passage (56). The return oil from the head end of the boom cylinders in passage (56) combines with the oil delivery from the right pump. This combined oil now flows to the rod end of the boom cylinders.

The oil delivery from only the right pump is used for the BOOM LOWER operation. Since the boom regeneration valve supplies return oil from the head end to the rod end of the boom cylinders, more efficient use of the oil delivery from the right pump is achieved during a BOOM LOWER operation.

Caterpillar Information System:

345C Material Handler Hydraulic System Swing Hydraulic System
345C Material Handler Hydraulic System Stick Hydraulic System
345C Material Handler Hydraulic System Boom Hydraulic System
M313C, M315C, M316C, M318C, M322C, M318C MH and M322C MH Wheeled Excavators Hydraulic System Boom Dampening System
Tier I Level Emssions Engine Repower for a 245/245B Hydraulic Excavator{1000} Tier I Level Emssions Engine Repower for a 245/245B Hydraulic Excavator{1000}
345B Series II Excavator Daily Inspection
C7 Engine for 584 and 584HD Forwarders and for 525C, 535C, and 545C Wheel Skidders E194 High Exhaust Temperature
345C Material Handler Hydraulic System Negative Flow Control System
345C Material Handler Hydraulic System Main Control Valve
330C With Drilling Front Machine System Specifications Air Cleaner
345C Material Handler Hydraulic System Main Hydraulic System
330C Excavator Specifications - Long Reach Configuration with a Two-Position Retrofit Boom
325C LCR Excavator Hydraulic System Relief Valve (Swing)
C15 and C18 Engines for Caterpillar Built Machines Elevated Idle
345C Material Handler Hydraulic System Travel Hydraulic System
C11 and C13 Engines Engine Mounting
M325C Excavator Engine Supplement Oil Pan - Remove and Install - Engine in Chassis
C9 Engines for Caterpillar Built Machines General Information
C15 and C18 Engines for Caterpillar Built Machines CID 1421 FMI 09 Unable to communicate with Rear Engine ECM
C9 Engines for Caterpillar Built Machines Lubrication System
302.5C Mini Hydraulic Excavator Machine System Specifications Swing Boom Cylinder
C9 Engines for Caterpillar Built Machines Cooling System - Test
302.5C Mini Hydraulic Excavator Machine System Specifications Blade Lift Cylinder
330C Excavator Hydraulic System Hydraulic System Pressure - Release