Platform - Remove and Install
Removal Procedure
Start By:
- Remove the thickness control groups. Refer to Disassembly and Assembly, "Thickness Control - Remove".
- Remove bolts (2) and walkways (1) .
Show/hide table
Illustration 1 | g01303516 |
- Cut cable straps (3) and move harness assembly (4) out of the way.
- Remove bolts (6) and lower screed control box (5) out of the way.
Show/hide table
Illustration 2 | g01303522 |
- Remove bolts (7) and hand rails (8). Repeat the same procedure on the other side of the screed.
Show/hide table
Illustration 3 | g01303547 |
- Remove bolts (9) and walkway (10). Repeat the same procedure on the other side of the screed.
Show/hide table
Illustration 4 | g01303573 |
- Remove cap (12) from both sides of the main walkway. Attach a suitable lifting device and remove main walkway (11). The weight of main walkway (11) is approximately 73 kg (161 lb).
Show/hide table
Illustration 5 | g01303606 |
- Remove bolts (13) and platform support (14). Repeat the same procedure on the other side of the screed.
Show/hide table
Illustration 6 | g01303619 |
- Remove screw (15) in order to separate the main harness assembly from harness assembly (17). Remove screws (16) in order to remove harness assembly (17). Repeat the same procedure on the other side of the screed.
Show/hide table
Illustration 7 | g01303624 |
- Remove bolts (19) and control box (18). Repeat the same procedure on the other side of the screed.
Show/hide table
Illustration 8 | g01303703 |
- Cut cable straps (21) in order to move harness assembly (20) out of the way.
Show/hide table
Illustration 9 | g01303706 |
- Cut cable straps (23) in order to move hose assembly (22) out of the way.
Show/hide table
Illustration 10 | g01303707 |
- Disconnect harness assemblies (24) .
Show/hide table
Illustration 11 | g01303713 |
- Disconnect harness assembly (27). Remove bolt (25) and horn (26) .
Show/hide table
Illustration 12 | g01303714 |
- Remove bolts (29) and platform support (28). Attach a suitable lifting device and remove platform support (28). The weight of platform support (28) is approximately 28 kg (62 lb). Repeat the same procedure on the other side of the screed.
Show/hide table
Illustration 13 | g01303718 |
Installation Procedure
- Attach a suitable lifting device to platform support (28). The weight of platform support (28) is approximately 28 kg (62 lb). Install platform support (28) and bolts (29). Repeat the same procedure on the other side of the screed.
Show/hide table
Illustration 14 | g01303718 |
- Install horn (26) and bolt (25). Connect harness assembly (27) .
Show/hide table
Illustration 15 | g01303714 |
- Connect harness assemblies (24) .
Show/hide table
Illustration 16 | g01303713 |
- Place hose assembly (22) against links and install cable straps (23) .
Show/hide table
Illustration 17 | g01303707 |
- Place harness assembly (20) against links and install cable straps (21) .
Show/hide table
Illustration 18 | g01303706 |
- Install control box (18) and bolts (19). Repeat the same procedure on the other side of the screed.
Show/hide table
Illustration 19 | g01303703 |
- Install harness assembly (17) and screws (16). Connect the main harness assembly to harness assembly (17). Install screw (15). Repeat the same procedure on the other side of the screed.
Show/hide table
Illustration 20 | g01303624 |
- Install platform support (14) and bolts (13). Repeat the same procedure on the other side of the screed.
Show/hide table
Illustration 21 | g01303619 |
- Attach a suitable lifting device and install main walkway (11). The weight of main walkway (11) is approximately 73 kg (161 lb). Install cap (12) to both sides of the main walkway.
Show/hide table
Illustration 22 | g01303606 |
- Install walkway (10) and bolts (9). Repeat the same procedure on the other side of the screed.
Show/hide table
Illustration 23 | g01303573 |
- Install hand rails (8) and bolts (7). Repeat the same procedure on the other side of the screed.
Show/hide table
Illustration 24 | g01303547 |
- Install screed control box (5) and bolts (6) .
Show/hide table
Illustration 25 | g01303522 |
- Place harness assembly (4) against links and install cable straps (3) .
Show/hide table
Illustration 26 | g01303516 |
- Install walkways (1) and bolts (2) .
End By: Install the thickness control groups. Refer to Disassembly and Assembly, "Thickness Control - Install".
Caterpillar Information System:
AS3301C Asphalt Screed Drop Arm - Install
AS3301C Asphalt Screed Drop Arm - Assemble
AS3301C Asphalt Screed Drop Arm - Disassemble
793D Off-Highway Truck Jacking Locations
AS3301C Asphalt Screed Drop Arm - Remove
C9 Engines for Motor Graders Sensor Signal (Analog, Passive) - Test
TK711, TK721, TK722, TK732, TK741, TK751 and TK752 Track Feller Bunchers IQAN MDM Monitor Fault ; Event Codes VREF-A Error IQAN Lx A0
G3600 Engines ECM Software - Install
AS3251C Asphalt Paver Chain (Crown) - Remove and Install
450E Backhoe Loader Hydraulic and Steering System Hydraulic Hand Control (Backhoe)
2006/11/27 An Updated Gasket for the Water Temperature Regulator Housing is Available {1355, 1380, 1393}
2006/11/27 An Updated Gasket for the Water Temperature Regulator Housing is Available {1355, 1380, 1393}
AS3251C Asphalt Paver Screed - Remove and Install
AS3251C Asphalt Paver Thickness Control - Remove
AS3301C Asphalt Screed Thickness Control - Disassemble
AS3301C Asphalt Screed Thickness Control - Assemble
AS3251C Asphalt Paver Thickness Control - Install
C11 and C13 Engines and 14M and 16M Motor Graders Sensor Supply - Test
G3304B and G3306B Engines Valve Lash Is Excessive
C11 and C13 Engines and 14M and 16M Motor Graders Shutdown (Ground Level) - Test
TK711, TK721, TK722, TK732, TK741, TK751 and TK752 Track Feller Bunchers IQAN MDM Monitor Fault ; Event Codes VREF-A Error IQAN Lx A1
2006/10/23 New Relief Valves Are Used in the Main Control Valve {5051, 5069}
TK711, TK721, TK722, TK732, TK741, TK751 and TK752 Track Feller Bunchers IQAN MDM Monitor Fault ; Event Codes Module is Off-Line IQAN Lx A0
793D Off-Highway Truck Engine Supplement Water Temperature Regulator - Remove and Install