Track - Remove and Install - Steel Track
- Position the machine on firm, level ground.
- Remove any work tool that is attached to the quick coupler.
- Raise the loader arms and install the brace for the loader lift arm. Refer to Operation and Maintenance Manual, "Loader Lift Arm Brace Operation".
Show/hide table
Illustration 1 g03653183 - Use an appropriate floor jack to lift the machine off the ground. Use appropriate jack stands to block up the machine. Raise the machine until tracks are approximately
50 mm (2.0 inch) (A) off the ground. - Detention the track. Refer to Operation and Maintenance Manual, "Track (Steel) - Inspect/Adjust".
Show/hide table
Illustration 2 g03653221 (1) Final Drive Sprocket
(2) Front idler wheelNote: The approximate weight of the track is
400 kg (882 lb) . - Use a suitable method to flag the track shoe over the master link so that the track location can be seen from the operator station.
Show/hide table
Illustration 3 g03653793 (2) Front Idler Wheel
(3) Flagged Track over Master Link
(4) Lifting Device Location - Operate the machine drive control to position the flagged track shoe at the top of the front idler & shut off the machine.
- Attach a suitable lifting device to the track just behind the flagged track shoe.
Show/hide table
Illustration 4 g03653779 Route strap through debris openings. - Use suitable blocking material in front of the front idler to catch the forward portion of the track
Show/hide table
Illustration 5 g03653821 - Remove the four master link bolts of the flagged track shoe over the master link and remove the track shoe.
Show/hide table
Illustration 6 g03653829 - Lift the strapped rear portion of the track and over the sprocket and lay this portion on the ground behind the machine.
- Repeat steps 6 through 11 for the other side.
Note: The approximate weight of the track is
- Unroll out the track assembly on a flat, level surface. Ensure that the two master links are free of any paint and primer. Orient the track assembly so the leading edge of the track shoes face forward when on the top of the undercarriage.
Show/hide table
Illustration 7 g03653200 - Use suitable lifting or moving equipment to lay out the track under the undercarriage. Ensure that placement of the track allows enough length behind the machine to wrap over the sprocket.
- Use an appropriate lifting device. Strap the track by routing a lifting sling through the debris openings of the rear most track shoe
- Lift the rear portion of the track over the sprocket, engaging enough teeth to retain the weight of the track.
- Lift the front portion of the track over the carrier roller. Use suitable blocking material at the front idler to prevent the track from slipping off the undercarriage.
- Connect the two master links insuring all the teeth align. Secure the two links together with four master link bolts. Torque the master link bolts to
280 ± 15 N·m (206.5 ± 11.1 lb ft) .Show/hide tableIllustration 8 g03653842 - Check and adjust the alignment of the carrier roller. Align the center of the carrier roller with the center of the link assembly (6).
- Loosen the carrier roller alignment bolt (5) to shift the roller assembly as needed.
- Tighten the carrier alignment bolt (5) to a torque of
186 ± 10 N·m (137.2 ± 7.4 lb ft) . - Remove blocking and strapping.
Caterpillar Information System:
299D2 and 299D2 XHP Compact Track Loaders, 297D2 and 297D2 XHP Multi Terrain Loaders and 272D2 and 272D2 XHP Skid Steer Loaders Power Train Idler - Remove and Install - Single Flange
740 Ejector Articulated Truck Engine Compression Brake Valve Lash - Check
740 Ejector Articulated Truck Capacities (Refill)
740 Ejector Articulated Truck Additional Messages
740 Ejector Articulated Truck Tire Shipping Pressure
299D2 and 299D2 XHP Compact Track Loaders, 297D2 and 297D2 XHP Multi Terrain Loaders and 272D2 and 272D2 XHP Skid Steer Loaders Power Train Track Roller - Remove and Install
426F2 Back Hoe Loader Machine System Bank Valve (Backhoe) - Install
New Pinion Gear and Pinion Bolt are Now Used on Certain 797, 797B and 797F Off-Highway Trucks {3254, 3256, 3258} New Pinion Gear and Pinion Bolt are Now Used on Certain 797, 797B and 797F Off-Highway Trucks {3254, 3256, 3258}
426F2 Back Hoe Loader Machine System Lift Arms - Remove and Install - Parallel Lift
773E Off-Highway Truck Engine Supplement Aftercooler - Install
773E Off-Highway Truck Engine Supplement Aftercooler - Remove
422F2, 427F2, 428F2, 432F2, 434F2 and 444F2 Backhoe Loaders Hydraulic and Steering System Control Valve - Hammer
773E Off-Highway Truck Power Train Transmission Planetary and Transfer Gears - Remove
773E Off-Highway Truck Power Train Transmission Planetary and Transfer Gears - Install
New Software Version Is Now Available for Cat® Terrain for Drilling {7605, 7610, 7620} New Software Version Is Now Available for Cat® Terrain for Drilling {7605, 7610, 7620}
426F2 Backhoe Loader Power Train Transmission (Direct Drive) - Install
773E Off-Highway Truck Machine Systems Electronic Control Module (Traction Control System) - Remove and Install
773E Off-Highway Truck Machine Systems Electronic Control Module (Payload) - Remove and Install
3512E Engines for Caterpillar Built Machines Electronic Control (Diesel Exhaust Fluid) - Remove and Install
C13, C15, and C18 Generator Set Engines CID 1922 FMI 05 Intake Valve Actuation System Oil Pressure Solenoid Current Below Normal
C13, C15, and C18 Generator Set Engines CID 1922 FMI 06 Intake Valve Actuation System Oil Pressure Solenoid Current Above Normal
797F Off-Highway Truck Field Assembly Cooling System Package - Install - High Altitude
784C and 785C Off-Highway Truck/Tractors Suspension Head (Front) - Inspect
PM620, PM622, PM820 and PM822 and PM825 Cold Planer Power Train Drive Sprocket