Usage:

All Remanufactured Engines and Short Blocks

It is important and necessary that a short block or a remanufactured engine have adequate (needed) lubrication during the first few seconds of the initial (first) start-up of the engine. A start without the needed lubrication for these engines can cause bearing damage.

It is our recommendation to always do the PRESSURE LUBRICATION PROCEDURE given in this instruction, before the initial start of a reconditioned or rebuilt engine.

Pressure Lubrication Procedure


NOTICE

Some type of oil reservoir with a pressure gauge is needed to do the pressure lubrication. In the procedure that follows, a tank assembly from a 1P540 Flow Checking Tool Group is used as an example. If one of these tanks is used to do the pressure lubrication, the inside of the tank must be completely clean. Never use the same tank assembly for both pressure lubrication and for fuel flow checking. It is not possible to get the tank assembly clean enough to do both operations. Any amount of dirt, debris, etc., can cause fuel nozzle failure, when the tank is used for fuel flow checking. Other sources of clean oil under pressure, such as a service shop central oil supply, can also be used for pressure lubrication.


------ WARNING! ------

Air pressure must not be more than 50 psi (345 kPa) at any time.

-------WARNING!-------

(1) Adjust the air pressure regulator to 35 ± 5 psi (240 ± 35 kPa).

(2) See the LUBRICATION AND MAINTENANCE GUIDE for the engine model that is to have the pressure lubrication, and find the amount of oil that is needed to fill the engine crankcase to the correct oil level. Put 30% of this amount of oil in the tank assembly for use in the pressure lubrication procedure.

NOTE: For some engines, 30% of the crankcase capacity will make it necessary to fill the tank assembly, shown here, more than one time.

(3) For pressure lubrication of an engine, use the necessary fittings and hose to connect the tank assembly to a port that connects to the main oil gallery of the cylinder block. Illustrations (A), (B) and (C) above are examples of engine models. For engine models (A), remove a plug at the rear of the right side cylinder head and make the connection as shown. For engine models (B) and (C), remove a plug (1) or (2) on the right side of the cylinder block and connect the pressure lubrication equipment.

(4) Connect shop air pressure to the tank assembly [tank assembly air pressure regulator must be adjusted to 35 ± 5 psi (240 ± 35 kPa)] to move the oil from the reservoir into the main oil gallery and engine lubrication passages.

NOTE: If shop air pressure is not available, the tank assembly shown has a hand pump that can be used to get the minimum pressure needed.

(5) After the pressure lubrication procedure is complete, shut off the air pressure and disconnect the pressure lubrication equipment. Be sure to install the plug in the hole that was used for pressure lubrication.

(6) Add the remainder of oil needed to fill the engine crankcase to its correct level. Remember that 30% of the oil needed to fill the crankcase has already been installed during the pressure lubrication procedure.

NOTE: Before the engine is started, turn the engine a few revolutions with the governor control in the FUEL OFF position, to get movement of the lubrication oil within the engine.

Caterpillar Information System:

Installing Heli-Coil Inserts In Caterpillar Cylinder Heads{1117} Installing Heli-Coil Inserts In Caterpillar Cylinder Heads{1117}
Installation Of 8N6287 Fuel Priming Knob Kit{1258} Installation Of 8N6287 Fuel Priming Knob Kit{1258}
Installation Of 5N7499 And 5N7500 Front Power Take-Off Groups{3107} Installation Of 5N7499 And 5N7500 Front Power Take-Off Groups{3107}
Use Of 1P3550 Wiring Harness Tester Group (24 Volt){0709, 3168} Use Of 1P3550 Wiring Harness Tester Group (24 Volt){0709, 3168}
Use Of 6V3025 Battery Cable Repair Kit{0613, 1400} Use Of 6V3025 Battery Cable Repair Kit{0613, 1400}
Installation Of 3N6351, 3N8285, 3N9095 And 7T5287 Modulating Valve Groups In Marine Transmissions{3300} Installation Of 3N6351, 3N8285, 3N9095 And 7T5287 Modulating Valve Groups In Marine Transmissions{3300}
Installation Of 5N7375, 5N7376 And 5N7377 Enclosure Groups For Package Generator Sets{7002} Installation Of 5N7375, 5N7376 And 5N7377 Enclosure Groups For Package Generator Sets{7002}
Installation Of 4W9528 Enclosure Group For Package Generator Sets{7002} Installation Of 4W9528 Enclosure Group For Package Generator Sets{7002}
Use Of 6V200 Hydraulic Wrench{0614, 0623} Use Of 6V200 Hydraulic Wrench{0614, 0623}
Service Information And Instructions For Use of 5P8585 Leak Detector{0651, 7320} Service Information And Instructions For Use of 5P8585 Leak Detector{0651, 7320}
installation of 9n6275 cylinder sleeve{1222} installation of 9n6275 cylinder sleeve{1222}
Installation Of 2N7003 Soot Filter{1054} Installation Of 2N7003 Soot Filter{1054}
Installation Of 5N5880 Remote Shut-Off Group And 5N6336 Gauge Group{7400, 7418} Installation Of 5N5880 Remote Shut-Off Group And 5N6336 Gauge Group{7400, 7418}
Installation Of Replacement Drive Sleeve For Marine Transmission Oil Pump{3310} Installation Of Replacement Drive Sleeve For Marine Transmission Oil Pump{3310}
Use Of 8T0455 Cylinder Liner Projection Indicator Group{0760, 1216} Use Of 8T0455 Cylinder Liner Projection Indicator Group{0760, 1216}
Use Of FT1525 Alignment Pin, FT1526 Salvage Fixture And FT1698 Bearing Installation Tool For Reconditioning Of 3208 Governor Housings{1265, 1264} Use Of FT1525 Alignment Pin, FT1526 Salvage Fixture And FT1698 Bearing Installation Tool For Reconditioning Of 3208 Governor Housings{1265, 1264}
Installation Of 8N6414 Ether Starting Aid Group{1456} Installation Of 8N6414 Ether Starting Aid Group{1456}
2W715 Turbocharger Cartridge Repair Kit{1053} 2W715 Turbocharger Cartridge Repair Kit{1053}
Installation Of Replacement Parts For 3N7722, 8N2744, 1W1872, 1W1873, 1W1881 and 1W1882 Engine Oil Pump Groups{1304} Installation Of Replacement Parts For 3N7722, 8N2744, 1W1872, 1W1873, 1W1881 and 1W1882 Engine Oil Pump Groups{1304}
Installation of 5N7710 Fuel Injection Lines Group And 5N7741 Fuel Lines Drain Group{1250} Installation of 5N7710 Fuel Injection Lines Group And 5N7741 Fuel Lines Drain Group{1250}
Installation Of Electric (Digital) Tachometer Groups{7462} Installation Of Electric (Digital) Tachometer Groups{7462}
Use Of 6V4141 Sleeve Metering Calibration Tool Group{0778, 0782} Use Of 6V4141 Sleeve Metering Calibration Tool Group{0778, 0782}
Installation Of 1W4793 Governor Spring (High Idle){1264, 1265} Installation Of 1W4793 Governor Spring (High Idle){1264, 1265}
Assembly Of 6V97 Engine Stand{0630} Assembly Of 6V97 Engine Stand{0630}
Back to top
The names Caterpillar, John Deere, JD, JCB, Hyundai or any other original equipment manufacturers are registered trademarks of the respective original equipment manufacturers. All names, descriptions, numbers and symbols are used for reference purposes only.
CH-Part.com is in no way associated with any of the manufacturers we have listed. All manufacturer's names and descriptions are for reference only.