UPS 250, UPS 300, UPS 500, UPS 600, UPS 750 and UPS 900 Uninterruptible Power Supply Caterpillar


Upper Bearing - Remove and Install

Usage:

UPS 250 APZ
Note: Whenever the upper bearing is replaced, the lower bearing must be replaced as well.

Removal Procedure

Table 1
Required Tools    
Tool     Part Number     Part Description     Qty    
A     191-5217     Guide Pin     1    
B     190-8385     Bearing Puller Gp     1    



Illustration 1g00985643

(1) (1) Screw

(2) Assembly (Rotor Position Sensor)

(3) O-ring

(4) Hex Bolt

(5) Wheel (Rotor)

(6) Spacer

(7) Screw

(8) Shipping Plug

(9) Plug with an O-ring

(10) O-ring

(11) Assembly (Top Bearing)

(12) Sensor (Vacuum)

(13) Assembly (Bottom Bearing)

(14) Spacer

(15) Retaining Bolt

(16) Mounting Hardware for the Drain (Charge)

(17) Mounting Hardware for the Drain (Charge)

(18) Drain (Charge)

(19) Load Plate

(20) Shims (Load Cell)

(21) Load Cell and Base Plate Assembly

(22) Hex Bolt

(23) Spacer

(24) Hex Bolt with Polished Head

(25) Screw

(26) O-ring

(27) Assembly (Static Drain)

  1. Shut down the System before attempting to remove the upper bearing. Refer to Testing and Adjusting, "System Shutdown" for the proper shutdown procedure.



    Illustration 2g00843202

  1. Remove vacuum hose (30) from the system. This relieves the vacuum from the system.

  1. Disconnect the yellow connector for the thermistor and the 19 pin instrument connector.

  1. Remove three screws (1) .

  1. Remove assembly (Rotor Position Sensor) (2) .

  1. Remove O-ring (3) .

  1. Remove bolt (4) .

  1. Remove commutation sensor wheel (5) .

  1. Remove spacer (6) .



    Illustration 3g00852370

  1. Use four feeler gauges. Measure the gap that is between the bearing cartridge and the end plate. Take measurements at four locations.

    The measurements will be used during the installation of the new bearing. Record the results in the following table.

    Table 2
    Location     Measurement    
    1        
    2        
    3        
    4        

  1. Loosen eight screws. Use quarter turns. Use a star pattern.

  1. Install a 191-5217 Guide Pin in one of the eight bolt holes that are located in the bearing cartridge. This will prevent the bearing cartridge from turning.

    Note: The location for the connector for the cable (thermistor) must be maintained when the bearing is reinstalled.




    Illustration 4g00852427

    190-8385 Bearing Puller Gp

  1. Install the 190-8385 Bearing Puller Gp on the bearing cartridge.

    Reference: Refer to Illustration 4.

  1. Turn center bolt (20) clockwise until the bolt contacts the bearing shaft.

  1. Turn center bolt (20) in order to remove the bearing cartridge.



    Illustration 5g00863802

    (35) Bearing Cartridge

    (36) O-ring

    (37) Brass Shim

  1. Remove brass shim (37) from bearing cartridge (35).

  1. Measure the old brass shim and record the measurement.

    Each bearing cartridge has a unique shoulder height. The height is stamped on the cartridge. The shims are added in order to adjust the height of the shoulder. Record the height of the shoulder.

    Table 3
    Bearing Measurements    
    Old Brass Shim Thickness        
    Old Shoulder Height        

    Save the brass shim. The shim may be used during the installation procedure.

Installation Procedure

Table 4
Required Tools    
Tool     Part Number     Part Description     Qty    
A     191-5217     Guide Pin     2    
B     190-8379     Bearing Installer Gp     1    
C     7M-7456     Bearing Mount Compound     1    
D     190-8380     Spare Shim Kit  (1)     1    
E     6V-2055     High Vacuum Grease     1    
( 1 ) The kit contains the following brass shims: Eight 190-8381 Brass Shim (0.05 mm), Four 190-8382 Brass Shim (0.13 mm), Two 190-8383 Brass Shim (0.25 mm) and One 190-8384 Brass Shim (0.50 mm)



Illustration 6g00985643

(1) (1) Screw

(2) Assembly (Rotor Position Sensor)

(3) O-ring

(4) Hex Bolt

(5) Wheel (Rotor)

(6) Spacer

(7) Screw

(8) Shipping Plug

(9) Plug with an O-ring

(10) O-ring

(11) Assembly (Top Bearing)

(12) Sensor (Vacuum)

(13) Assembly (Bottom Bearing)

(14) Spacer

(15) Retaining Bolt

(16) Mounting Hardware for the Drain (Charge)

(17) Mounting Hardware for the Drain (Charge)

(18) Drain (Charge)

(19) Load Plate

(20) Shims (Load Cell)

(21) Load Cell and Base Plate Assembly

(22) Hex Bolt

(23) Spacer

(24) Hex Bolt with Polished Head

(25) Screw

(26) O-ring

(27) Assembly (Static Drain)

Each bearing cartridge has a unique shoulder height. The height is stamped on the cartridge. Shims are added in order to adjust the height of the shoulder.

  1. Compare the shoulder height of the old bearing cartridge and the shoulder height of the new bearing cartridge. When brass shims are needed, add brass shims or subtract brass shims. The tolerance of the measurement is ± 0.0508 mm (± 0.002 inch).

    Table 5
    Bearing Measurements    
    Old Brass Shim Thickness        
    Old Shoulder Height (1)        
    New Shoulder Height (1)        
    New Brass Shim Thickness        
    ( 1 ) The Shoulder Height is stamped on the shoulder.



    Illustration 7g00863802

    (35) Bearing Cartridge

    (36) O-ring

    (37) Brass Shim

  1. Apply 6V-2055 High Vacuum Grease to O-ring (36).

  1. Install O-ring (36) on bearing cartridge (35) .

  1. Install another 191-5217 Guide Pin in one of the eight bolt holes that are located in bearing cartridge (13). This pin should be installed 180° away from the first pin. This will locate the bearing cartridge during installation.

  1. Align the 4-pin connector for the thermistor so that the cable will reach the connector.

  1. Install the new bearing cartridge. Use your hand and seat the bearing cartridge.



    Illustration 8g00863883

    190-8379 Bearing Installer Gp

    (40) Nut

    (41) Center Bolt

  1. Install 190-8379 Bearing Installer Gp on the bearing housing.

    Reference: Refer to Illustration 8.

  1. Turn center bolt (41) clockwise until bearing cartridge (35) is approximately 12.7 mm (0.5 inch) from end plate (17) .

  1. Refer to "Removal Procedure" and then refer to illustration 3 for the position of the feeler gauges.

  1. Position the 4 feeler gauges.

  1. Turn nut (40). Seat the bearing cartridge.

  1. Remove the two 191-5217 Guide Pins .

  1. Install eight screws. Use quarter turns. Tighten the screws in a star pattern. Torque the screws to 27.1 N·m (20 lb ft).

  1. Remove the four feeler gauges.

  1. Install spacer (6) .

  1. Install commutation sensor wheel (5) .

  1. Clean the threads of bolt (4) with a wire brush or replace the bolt.

  1. Place one drop of 7M-7456 Bearing Mount Compound on the threads of bolt (4) .

  1. Install bolt (4). Torque the bolt to 38 N·m (28 lb ft).

  1. Apply 6V-2055 High Vacuum Grease to O-ring (3). Install the O-ring (3) in the commutation sensor assembly (2) .

  1. Install the assembly (Rotor Position Sensor) (2) so that the assembly points to the 1 o'clock and the 7 o'clock positions. The 12 o'clock position is the center of the back of the cabinet.

  1. Install three screws (1) .



    Illustration 9g00843202

  1. Apply 6V-2055 High Vacuum Grease to the O-ring for vacuum hose (30). Connect vacuum hose (30) .

  1. Connect the yellow connector for the thermistor and the 19 pin instrument connector.

  1. Refer to Testing and Adjusting, "Rotor Postion Sensor - Calibrate" and conduct the procedure.

Caterpillar Information System:

3408E and 3412E Industrial Engines Diagnostic Flash Code Retrieval
Electronic Modular Control Panel II (EMCP II) GSC CID 0100 - FMI 02 (for EUI Engines)
UPS 250, UPS 300, UPS 500, UPS 600, UPS 750 and UPS 900 Uninterruptible Power Supply Lower Bearing - Remove and Install
CIPI UNDERCARRIAGE Arrangements: 9Q-5262, 191-4041, and 204-9207 Travel Brake Valve - Install
3054 and 3056 Industrial and Generator Set Engines Engine Oil Cooler - Inspect
Electronic Modular Control Panel II (EMCP II) Indicators of Alarm Module Are Constantly Flashing
SPT343 Truck Mounted Pumper Model View Illustrations
CIPI UNDERCARRIAGE Arrangements: 9Q-5262, 191-4041, and 204-9207 Travel Brake Valve - Remove
CIPI UNDERCARRIAGE Arrangements: 9Q-5262, 191-4041, and 204-9207 Final Drive Sprocket - Remove and Install
UPS 250, UPS 300, UPS 500, UPS 600, UPS 750 and UPS 900 Uninterruptible Power Supply Fuse - Remove and Install
Electronic Modular Control Panel II (EMCP II) Display of Voltage or Current is Inaccurate
Electronic Modular Control Panel II (EMCP II) Display of Voltage or Current Is Zero
Electronic Modular Control Panel II (EMCP II) Spare Input/Output Programming OP6
Electronic Modular Control Panel II (EMCP II) Engine Setpoint Verification OP9
3126 Truck Engine Military Inlet Manifold - Remove
2001/12/01 Recommended Setting Of The Oil Mist Detector Alarm Changed {1336}
CIPI UNDERCARRIAGE Arrangements: 9Q-5262, 191-4041, and 204-9207 Swing Gear and Bearing - Remove
CIPI UNDERCARRIAGE Arrangements: 9Q-5262, 191-4041, and 204-9207 Swing Gear and Bearing - Install
3054 and 3056 Marine Generator Set Engines Engine Oil Filter Base - Remove - 3054 Engine
3054 and 3056 Marine Generator Set Engines Engine Oil Filter Base - Install - 3054 Engine
3126 Truck Engine Military Inlet Manifold - Install
3054 and 3056 Marine Generator Set Engines Engine Oil Filter Base - Remove - 3056 Engine
3054 and 3056 Marine Generator Set Engines Engine Oil Filter Base - Install - 3056 Engine
Electronic Modular Control Panel II (EMCP II) SP Fault Code